Solar Sanity Checksolar, decoded Independent. Nothing you type leaves your browser.

City of Lowell (AR)

Arkansas Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2020
Fire Setback Enforced0

Codes

NEC Code Version
2020
Code List

IBC 2021, IRC 2021

2021 ARKANSAS FIRE CODE I,II,III

2020 NATIONAL ELECTRIC CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

Revision Required
0
Rough Inspection
Rough Electrical
New Planset Required For Module Swap
1

Fire setbacks

Fire Setback Enforced
0
Setback Notes
Standard

Structural & loads

Wind Speed
107
Snow Load
10
Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Minimum Ground On Roof
#10

Electrical

AC Disconnect Required
Yes
Electrical Load Calcs Required
Derates
Allowed POI
Meter Adapter,Load Side Taps,Line Side Taps,PV Breaker
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.91

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes
Standard
Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Ground mount

Ground Mount Fencing Required
Mesh/Scrim