City of Bullhead City (AZ)
Codes
- NEC Code Version
- 2017
- Fire Code Version
- 2018 Building Code
- Code List
2018 INTERNATIONAL BUILDING CODE
2018 INTERNATIONAL RESIDENTIAL CODE
2018 INTERNATIONAL PLUMBING CODE
2018 INTERNATIONAL MECHANICAL CODE
2018 INTERNATIONAL FUEL GAS CODE
2018 INTERNATIONAL ENERGY CONSERVATION CODE
2018 INTERNATIONAL EXISITING BUILDING CODE
2018 INTERNATIONAL SWIMMING POOL AND SPA CODE
2017 NATIONAL ELECTRICAL CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- How Many Plansets Required
- 2
- Revision Required
- 1
- New Planset Required For Module Swap
- 0
Stamps
- Ee Stamp Required On SLD
- No
- Wet Stamps Required
- Digital Structural
- Structural Calculations Required
- Yes
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
At CR stage, create a related ticket to Permitting: "Please request the Plot Plans"
Structural & loads
- Wind Speed
- 90
- Wind Notes
Exposure Category B
- Snow Load
- 0
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Structural Notes
SE digital signature/stamp on corresponding PV pages & PE Letter / SE Calcs. Wind Speed: 90 mph, Exposure C Seismic Design Category: B
Engineer signature in color on planset
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Load Side Taps,Meter Adapter,PV Breaker,Line Side Taps
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Request plot plans from AHJ or Transfer measurements (perimeter, easements, etc.) from plot plans to your Site Plan. Reference -------> [Ware, Nadine. DCR 051321]
PROVIDE THE INSTALLATION INSTRUCTIONS FOR THE BATTERY
Provide an exterior elevation to show the following:
▪ Distance from grade to bottom of proposed battery bank.
▪ Distance from the top plate to the top of the proposed battery bank.
▪ Distance from all electrical equipment to the proposed battery bank.
▪ Distances between all existing and proposed electrical equipment.
o Provide the installation instructions for the Battery, etc. QR codes are not
acceptable.
A portion of the following comments below may apply to the battery bank, depending on the location.
Provide a floor plan of the interior of the garage.
To include the following:
• Size of garage, location of both vehicle doors.
• All existing appliances located in the garage.
• Location of the proposed battery bank.
• Distance of existing appliances to the proposed battery bank.
• Distance of parked vehicles to the proposed battery bank.
• A vehicle barrier to protect the battery bank. To be a minimum of a 3” metal bollard embedded 24” into concrete; 36” minimum above finished floor.
Provide a wall elevation to show the following:
• Distance from finished floor to bottom of proposed battery bank.
• Distance from the ceiling to the top of the proposed battery bank.
• Distance from any other appliances/electrical equipment to the proposed battery bank.
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- Yes - with dimensions
Plan set
- Plan Set Requirements
Planset AHJ Requirement Engineer stamped signature in color and Structural Calculations Engineer stamped signature in color.
H Frame for all manufactured homes, BOS cannot land on a manufactured home
Request plot plans from AHJ Transfer measurements (perimeter, easements, dimension etc.) from plot plans to your Site Plan.
Street address has to face down on the plans.
REVISIONS: Please RED cloud and Delta sign any changes made to the plans and provide the revision letter for the changes made.
Installation of solar panels on a manufactured home requires structural calculations. Provide one set with wet seal and signature. The second set may be a copy of the original. 2012 IRC / IBC and 2011 elec. Provide approval from Mohave Electric Cooperative Alternative Energy Department. All PV plan sheets are to be a minimum of 11 x 17 in size.
Show the distances between each existing and proposed electrical equipment.
- Site
We need to include a copy of the AHJ's plot plans on recorded with our PV plans submital. Request plot plans from AHJ . Transfer measurements (perimeter, easements, etc.) from plot plans to your Site Plan. **(THIS DOCUMENT NEEDS TO BE ATTAINED BY PERMITTING PRIOR TO COMING INTO PLANS STAGE)**
***PLOT PLAN -Lot dimensions, distances to property lines, 8’ PUE at front, etc., are to match what is shown for site plan***
Rotate property on site plan so that street and street name are at the bottom of page.
- Roof Plan Notes
All Jobs [THE PHOTOVOLTAIC SYSTEM SHALL BE INSTALLED IN ACCORDANCE WITH NEC 690 AND POSTED WITH APPLICABLE WARNINGS, SIGNAGE AND PLAQUES PER NEC 705- 10, 690-17, AND 690-64(b)(5).]
- Attachment Detail Notes
Per AHJ requirement All Pages with signatures the Planset & Structural Calculations are to be in color for printing
Show the distances between each existing and proposed electrical equipment.
- Electrical Diagram
Centerfed 120%: Not Sure Three Line and Single Line Required
- Custom Placards Required
- 0
- Non Standard Planset Requirements
- Single Line Diagram
- Non Standard Revision Requirements
REVISIONS: Please RED cloud and Delta sign any changes made to the plans and provide the revision letter for the changes made.
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim
- Ground Mount Notes
* Request plot plans from AHJ "" or "" Transfer measurements (perimeter, easements, etc.) from plot plans to your Site Plan.