City of Costa Mesa (CA)

California Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2023
Fire Code Version2018 Building Code
SolarAPP+ StatusAdopted
Wet Stamps RequiredNone
Fire Setback Enforced1

Codes

NEC Code Version
2023
Fire Code Version
2018 Building Code
Code List

2025 CALIFORNIA BUILDING CODE

2025 CALIFORNIA ELECTRICAL CODE

2025 CALIFORNIA FIRE CODE

2025 CALIFORNIA PLUMBING CODE

2025 CALIFORNIA MECHANICAL CODE

2025 CALIFORNIA ENERGY CODE

2025 CALIFORNIA RESIDENTIAL CODE

2025 CALIFORNIA ADMINISTRATIVE CODE

IEBC Accepted
1
ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Adopted
Any SolarAPP+ Restrictions
1
SolarAPP+ Restrictions
Existing Systems,Trenching,MPU
How Many Plansets Required
2
Revision Required
1
Rough Inspection
None
New Planset Required For Module Swap
0

Stamps

Ee Stamp Required On SLD
No
Wet Stamps Required
None
Structural Calculations Required
Yes - Attachment Spacing > 4ft
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes

Standard

Structural & loads

Wind Speed
110
Wind Notes

Exposure Category C

Snow Load
0
Reducible Snow Load Allowed
1
Max Attachment Spacing
48
Structural Notes
City of Costa Mesa requires the structural observation form to be filled out on their proprietary document. See __City of Costa Mesa - Structural Observation Report__ Form in the files section
Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
Load Side Taps,PV Breaker,Meter Adapter,Line Side Taps
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
1
BOS Restrictions

Standard

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes
  • Provide elevation view and show all equipment and window/door openings with distance to ESS
  • Batteries need 3' minimum clearance from any vents, windows, doors or other batteries
  • If Battery is more than 6ft away, disconnect is required at the ESS.

Battery in garage:

  • Provide barrier protection from vehicle if ESS located in direction path of vehicle.
  • Provide a floor plan with the interior clear dimensions of the garage, indicating that the proposed equipment is located outside of the required 20โ€™ x 20โ€™ clear space
  • Interconnected heat detectors required for all batteries installed inside garage/enclosed space
Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
Yes - with dimensions

Plan set

Cover Page

Fill out and uploaded City Standard Plan to CE-Solar Express Forms in LS.

Site

BOS equipment must be screened from public right of wall by a fence or wall. Indicate height of the fence to demonstrate that it will be tall enough to screen the equipment from view.

Roof Plan

Standoff shall not be allowed to be installed over eave areas without a structural analysis prepared by a California Engineer or Architect.

Attachment Detail

Use 4' attachment spacing to avoid engineering requirements

Electrical Diagram

Standard

Custom Placards Required
1
Placards Notes

Required for all jobs:

1. Structural observation letter from the architect or engineer will be required at final inspection.

2. Need large placard that reads:

  • "PHOTOVOLTAIC SYSTEM EQUIPPED WITH RAPID SHUTDOWN" with type 3/8" high on main panel
  • SPECIAL BATTERY PLACARD - "ESS EMERGENCY SHUTOFF" Placard needed on batteries in this AHJ
  • SPECIAL COMPANY INFO PLACARD REQUIRED AT MSP
Non Standard Revision Requirements

AHJ is extremely particular about all changes on the plans being red clouded. Anything on any page that even slightly changes must be clouded. Additionally, update the "revisions" section of the title block on the cover sheet to include the date of the latest revision.

Ground mount

Ground Mount Fencing Required
Mesh/Scrim
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the City of Costa Mesa (CA) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.