City of Fresno (CA)

California Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2023
Fire Code Version2018 Building Code
SolarAPP+ StatusAdopted
Wet Stamps RequiredNone
Fire Setback Enforced1

Codes

NEC Code Version
2023
Fire Code Version
2018 Building Code
Code List

2025 CALIFORNIA BUILDING CODE

2025 CALIFORNIA ELECTRICAL CODE

2025 CALIFORNIA FIRE CODE

2025 CALIFORNIA PLUMBING CODE

2025 CALIFORNIA MECHANICAL CODE

2025 CALIFORNIA ENERGY CODE

2025 CALIFORNIA RESIDENTIAL CODE

2025 CALIFORNIA ADMINISTRATIVE CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Adopted
Date SolarAPP+ Accepted
45062
Any SolarAPP+ Restrictions
1
SolarAPP+ Restriction Notes
  • Solaredge backup jobs with 63A breakers - Traditional submittal only - Solarapp will be rejected
SolarAPP+ Restrictions
Existing Systems,Trenching,Other
How Many Plansets Required
1
Revision Required
1
Rough Inspection
None
New Planset Required For Module Swap
0

Stamps

Ee Stamp Required On SLD
Yes - Derate
Wet Stamps Required
None
Structural Calculations Required
No
Ee Stamp Notes


Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Ridge Setback
36
Setback Notes
  • Fresno fire requires 36" setbacks on both sides of all horizontal ridges.
  • Setbacks to start at load bearing wall and not over unsupported eave
  • Setbacks must be drawn on all portions of the roof plan, setbacks cannot be 'assumed'

Structural & loads

Wind Speed
110
Wind Notes

Exposure Category B

Snow Load
0
Snow Load Notes

N/A

Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Minimum Ground On Roof
#10

Electrical

AC Disconnect Required
Yes
AC Disconnect Conditional Criteria
If battery is interior, an exterior AC disco is required
Electrical Load Calcs Required
Derates
Allowed POI
Load Side Taps,PV Breaker,Meter Adapter,Line Side Taps
Panel Schedule Required
Whole Home Backup
Temperature Rating
90
De Rating Ampacity
0.91

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

Battery [Producers storage device(s) will not cause the Host Load to exceed its normal peak demand. Normal peak demand is defined as the highest amount of power required from the Distribution System by Producers complete facilities without the influence or use of the energy storage device(s).]

  • On the ELD, identify what loads will be remaining in MSP

9540A accepted, manufacturer required spacing between batteries is allowed.

  • 3' from egress doors, windows, and all corners is still required
  • Ensure battery datasheet in plan set includes the 9540a listing.
Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Plan Set Requirements
  • Plans must include datasheets for every piece of new equipment being installed (Combiner panel, load centers, etc)
  • Plans should reference CA codes only, remove all references to National/International codes
  • AHJ is particular about text legibility, ensure all pages will have clear and legible text when printed

MPU

  • If using a solar ready MPU, include the spec sheets 

Existing Systems

  • Specify if existing system is rapid shutdown compliant or non-rapid shutdown compliant with leader
Cover Page Notes

All Jobs [ROOF ACCESS POINTS SHALL BE LOCATED IN AREAS THAT DO NOT REQUIRE THE PLACEMENT OF GROUND LADDERS OVER OPENINGS SUCH AS WINDOWS OR DOORS, AND LOCATED AT STRONG POINTS OF BUILDING CONSTRUCTION IN LOCATIONS WHERE THE ACCESS POINT DOES NOT CONFLICT WITH OVERHEAD OBSTRUCTIONS SUCH AS TREE LIMBS, WIRES OR SIGNS. // SHOW ON PLANS WHERE FIREFIGHTER ACCESS POINTS WILL BE LOCATED. CFC 1204.2. DISCONNECTING EQUIPMENT: ALL PHOTOVOLTAIC SOLAR POWER SYSTEM DISCONNECTING MEANS, INCLUDING RAPID SHUTDOWN EQUIPMENT SHALL BE INDICATING, OF AN APPROVED SIZE AND TYPE AND SHALL BE PLACED IN AN APPROVED POSITION THAT IS PLAINLY VISIBLE TO APPROACHING FIRE DEPARTMENT PERSONNEL. FMC 10- 51204.5.3. // DISCONNECTING MEANS SHALL HAVE A SIGN STATING EITHER ON/OFF OR ENERGIZED/NOT ENERGIZED . SHOW THIS SIGNAGE ON PLANS. \\\ RAPID SHUTDOWN SWITCH: A RAPID SHUTDOWN SHALL HAVE A LABEL LOCATED IN AN APPROVED .LOCATION, NOT GREATER THAN ONE FOOT FROM THE SWITCH AND THE LABELING SHALL BE PLACED IN A LOCATION THAT IS PLAINLY VISIBLE TO APPROACHING FIRE DEPARTMENT PERSONNEL. // LABELING SHALL BE REFLECTIVE AND BE OF SUFFICIENT DURABILITY TO WITHSTAND THE ENVIRONMENT INVOLVED AND SHALL BE MAINTAINED. THE LABELING SHALL STATE THE FOLLOWING: RAPID SHUTDOWN SWITCH FOR SOLAR PV SYSTEM FMC SECTION 10-501204.5.3. // LOCATIONS OF DC CONDUCTORS: CONDUIT, WIRING SYSTEMS AND RACEWAYS FOR PHOTOVOLTAIC CIRCUITS SHALL BE LOCATED AS CLOSE AS POSSIBLE TO THE RIDGE OR HIP OR VALLEY AND FROM THE HIP OR VALLEY AS DIRECTLY AS POSSIBLE TO REDUCE TRIP HAZARDS AND MAXIMIZE VENTILATION OPPORTUNITIES. // CONDUIT RUNS BETWEEN SUB ARRAYS AND TO DC COMBINER BOXES SHALL BE INSTALLED IN SUCH A MANNER THAT MINIMIZES THE TOTAL AMOUNT OF CONDUIT ON THE ROOF BY TAKING THE SHORTEST PATH FROM THE ARRAY TO THE DC COMBINER BOX. // THE DC COMBINER BOXES SHALL BE LOCATED SUCH THAT CONDUIT RUNS ARE MINIMIZED IN THE PATHWAYS BETWEEN ARRAYS. DC WIRING SHALL BE INSTALLED IN METALLIC CONDUIT OR RACEWAYS WHEN LOCATED WITHIN ENCLOSED SPACES IN A BUILDING. CONDUIT SHALL RUN ALONG THE BOTTOM OF LOAD BEARING MEMBERS.]

Site
  • Provide a scaled drawing showing the exact distance of structures on the property to the house and property line.
  • If structures are larger than 120 sq ft, a permit must be provided.
  • Provide a site plan that includes all structures on the property, drawn to scale (do not include RVs, canvas covers, or pop tents).
  • Show the dimensions of the property lines.
Site Notes

ALL JOBS [AC disconnect (if required) must be within line of sight to MSP]

Roof Plan
  • Setbacks must be drawn on all roof surfaces, setbacks cannot be 'assumed'
  • The layout of existing PV systems needs to be illustrated as individual modules, not as one large “obstruction.”
  • Layout of modules needs to be replicated in Aurora before downloading DXF
  • 3FT Setbacks required
Attachment Detail
  • Specify the maximum and minimum distance the PV modules are from the roofing material.
Electrical Diagram

Informational note:

  • If all equipment is accessible from outside and no gates block access, only one lockable AC disconnect is required within line of sight of the MSP/equipment.
  • If equipment or an ESS is located behind a gate, one of the following is required:
  • An AC conductor disconnect behind the gate, within line of sight of the equipment, and a separate lockable AC disconnect within line of sight of the MSP; or
  • A lockable AC disconnect within line of sight of the MSP only, which eliminates the need for an AC conductor disconnect behind the gate.
  • If a battery is installed in the garage, a separate AC conductor disconnect is required in the garage, in addition to a lockable AC disconnect within line of sight of the MSP.

All Jobs

  • AHJ DOES NOT ACCEPT OUR BUSBAR CERTS.

Derate

  • Provide picture of entire main panel, dead front and breakers in the plans.

Taps

  • Provide pictures of where tap will be in plans.

Battery

  • Provide load calcs for back up load panel.
  • Full panel schedule(s) required. MSP, sub panels, BLC, ISO.
  • Separate ESS disconnect required to comply with article 690.12c
Electrical Diagram Notes

Battery [Producers storage device(s) will not cause the Host Load to exceed its normal peak demand. Normal peak demand is defined as the highest amount of power required from the Distribution System by Producers complete facilities without the influence or use of the energy storage device(s).]

Existing Systems [Existing system is rapid shutdown compliant or non rapid shutdown compliant]

Label Page
  • Use 2017 Yellow, ensure all code reference are removed
  • Label Page should reference CA codes only.
  • AHJ requires a specific rapid shutdown label. Please see "RSD label" image in files section of this page for examples of the text required to be present on the label.
  • Color requirements for the labels are below:
  • 1. For solar photovoltaic systems that shut down the array and the conductors leaving the array, a label shall be provided. The first two lines of the label shall be uppercase characters with a minimum height of 3/8 inch (10 mm) in black on a yellow background. The remaining characters shall be uppercase with a minimum height of 3116 inch (5 mm) in black on a white background. 
  • 2. For photovoltaic systems that only shut down conductors leaving the array; a label shall be provided. The first two lines of the label shall be uppercase characters with a minimum height of 3/8 inch (10 mm) in white on a red background and the remaining characters shall be capitalized with a minimum height of 3/16 inch (5 mm) in black on a white background. The label shall be in accordance with Figure 1205.4.1(2). 
Custom Placards Required
1
Placards Notes
  • Standard Permanent Placards required, reflecting placards on plan set (Disconnect placards, main site placard at MSP)

Additional AHJ-specific placards

  • ESS JOBS - ESS Shutdown Placard Label
  • ESS JOBS - Placard at MSP detailing step by step how to shut system off
  • Special derate placard needed for derates. 'DO NOT UPSIZE - MAIN HAS BEEN DERATED'
  • Specify If Existing system is rapid shutdown compliant or non-rapid shutdown compliant with leader
Non Standard Revision Requirements
  • This AHJ is very particular about red clouding on revisions.
  • We must cloud every single change on the plans, and cannot cloud an entire page
  • The resubmission letter must also specifically explain the changes on each page.
  • DO NOT use abbreviations such as BOS, etc.

Ground mount

Ground Mount Fencing Required
Yes
Ground Mount Notes
  • Fencing is required for ground mounts
  • Fence must be 5ft high
  • Wire mesh type material is also acceptable, so long as it is flush mounted from ground to array. If meshing is plastic, must be UV rated.
  • Setbacks are a minimum of 5' from property lines or other structures
  • Accessory structures may not be located within the required 15' front setback.
  • A Special Inspection Letter for deep foundations is required. The AHJ stated that the soil engineers in town are generally also testing labs and can do the inspections required to obtain the letter. The reviewer gave no recommendation but listed some of the available businesses in the area who provide the service: TECHNICON, Sees, Krazan, Moore Twining, Salem, and RMA.
Ground Mount Requires Soil Sample
Soil Study
Setback Front Yard
15
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the City of Fresno (CA) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.