City of Menifee (CA)
Codes
- NEC Code Version
- 2023
- Fire Code Version
- 2018 Building Code
- Code List
2025 CALIFORNIA BUILDING CODE
2025 CALIFORNIA ELECTRICAL CODE
2025 CALIFORNIA FIRE CODE
2025 CALIFORNIA PLUMBING CODE
2025 CALIFORNIA MECHANICAL CODE
2025 CALIFORNIA ENERGY CODE
2025 CALIFORNIA RESIDENTIAL CODE
2025 CALIFORNIA ADMINISTRATIVE CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- SolarAPP+ Status
- Adopted
- Date SolarAPP+ Accepted
- 44368
- Any SolarAPP+ Restrictions
- 1
- SolarAPP+ Restrictions
- Existing Systems,Trenching,MPU
- How Many Plansets Required
- 1
- Revision Required
- 1
- Rough Inspection
- None
- New Planset Required For Module Swap
- 0
Stamps
- Ee Stamp Required On SLD
- Yes - MPU
- Wet Stamps Required
- None
- Structural Calculations Required
- Yes - Existing PV
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 110
- Wind Notes
Exposure Category C
- Snow Load
- 0
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Structural Notes
- Standard
- Minimum Ground On Roof
- #10
Electrical
- AC Disconnect Required
- Yes
- Electrical Load Calcs Required
- Derates
- Allowed POI
- PV Breaker,Meter Adapter
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
- BOS Restrictions
Standard
Battery / ESS
- Unique Battery Placards Needed
- 1
- ESS Notes
Per corrections on staff 431034, SEEB & Enphase batteries do NOT require ESS disconnects.
WHEN DOING A BATTERY BACKUP SYSTEM. PLEASE ATTACH DOCUMENT BELOW.
Please comply with California Fire code 1206.2
Detail on plans:
- #1 Location and layout of the room where the batteries are installed.
- #2 Details on the fire-resistance-rated assemblies.
- #3 quantities and types of batteries
- #4 manufactures specifications and ratings
- #5 Details on energy management system.
- #6 location and content of signage.
- #7 Details of fire extinguishing and smoke detection system.
- #8 Rack storage arrangement and seismic support.
Please clarify how emergency services would shut down all PV including the battery back up. This must be done within 3 feet of the service entrance.
Please add a really accessible emergency service disconnect within 3 feet of the main service panel. It must shut down all solar and battery systems per code section 110.25, 705.22,705.23, 705.31, 706.7, 706.30
ESS disconnect required when the ESS is
more than 10 feet, separated by a gate or not
within line of sight of the service disconnect
When ESS are installed inside a garage, there must be an approved heat detector interconnected with the existing alarm system.
The elevation diagram must show elevation of all equipment along with measurements between equipment, gates, windows and doors.
ESS disconnect required within 6ft of MSP on same wall and not blocked by walls/gates/etc
Accepts 9540A spacing.
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- Yes - with dimensions
Plan set
- Plan Set Requirements
Please indicate roof coverage percentage for ALL SOLAR and do not include any patio covers (if any)
- Cover Page
Minimum size 14 font required on text throughout plan set
MPU requires panel upgrade permit first.
- Site
Indicate all existing structures on property
Indicate existing wall, fence or gate
AC disconnects required if inverter is not within line of sight of MSP
- Site Notes
Battery [ESS will not be within 3' of a door or window]
- Roof Plan
On a separate page, show rafter/truss layout, array supports (rails), roof penetrations, and connections to the roof-framing members (attachments).
Show the conduit run and indicate how far the conduit is mounted off the roof deck
- Attachment Detail
please show the truss layout and specific attachment detail
Please show ESS Mounting Details
- Electrical Diagram
All Projects:
- Required to show all breakers in Sub Panel.
- Required to show the wire size between the Main Panel and Sub Panel.
- The Breaker for Sub Panel in the Main Panel can not exceed the Sub Panel Main Breaker rating.
- Text on the line diagram cannot be smaller than size 12.
- Centerfed 120% allowed
Add-on System:
- If the disconnect only shut down a portion of the system it will need to be labeled accordingly.
- Please identify all disconnects and what they shut down.
EV Chargers:
- Add EV Charger to Load Calc's
- Add EV Charger in Directory Placard
- Indicate EV Charger integrated to the inverter in the line diagram
- Indicate EV charger station on the scope of work. Could be combined with the inverter see note for EV Charger to clarify to AHJ
DERATES:
- Include the torque wrench serial number, calibration date, and certification number on the ELD
- Include a datasheet for the derated main-breaker we are installing (Google the existing MB part #, with the new amperage + datasheet)
Serial number 204230301
Calibration date - 4/12/2023
Certificate number - 51-01895
MPU:
- need to provide the existing MSP bus and breaker rating on ELD
- Electrical Diagram Notes
All Jobs [IF UFER IS NOT ACCESSIBLE OR VERIFIABLE INSTALL (2) NEW 5/8"ร X 8' LONG, 6 FEET APART GROUNDING RODS AND BOND SOLAR SYSTEM EQUIPMENT GROUNDING ACCORDINGLY. PER NEC 250]
- Label Page
Use NEC 2020 in the label dropdown
Do not use Menifee Placard
Site placard: The orientation of the house must match the layout when looking at the placard
- Custom Placards Required
- 1
- Placards Notes
- If more than 1 ESS installed - Batteries must have naming placard: "Battery 1" "Battery 2" etc
- Permanent hard Main Site Placard + BOS hard placards required
- Non Standard Revision Requirements
You must provide a correction letter stating all the corrections and how they were corrected along with clouding the plans and adding "deltas" with revision dates next to each clouded section.
Ground mount
- Ground Mount Fencing Required
- Yes
- Ground Mount Notes
If the inverter is on the array, we need to have an AC disco next to the inverter.
Add note, Conduit depth must be 24 inches to the top of the pipe under drivable areas
Provide details for fencing, if applicable
Distance from house to GM array required
for septic records: Request for Public Records | Riverside County Department of Environmental Health
- Setback Front Yard
- 25
- Setback Back Yard
- 25
- Setback Side Yard
- 20