NEC Code Version2023
Fire Code Version2018 Building Code
SolarAPP+ StatusTargeted
Fire Setback Enforced1

Codes

NEC Code Version
2023
Fire Code Version
2018 Building Code
Code List

2025 CALIFORNIA BUILDING CODE

2025 CALIFORNIA ELECTRICAL CODE

2025 CALIFORNIA FIRE CODE

2025 CALIFORNIA PLUMBING CODE

2025 CALIFORNIA MECHANICAL CODE

2025 CALIFORNIA ENERGY CODE

2025 CALIFORNIA RESIDENTIAL CODE

2025 CALIFORNIA ADMINISTRATIVE CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Targeted
Any SolarAPP+ Restrictions
1
SolarAPP+ Restrictions
MPU,Derate
How Many Plansets Required
1
Revision Required
0
New Planset Required For Module Swap
0

Stamps

Structural Calculations Required
Yes

Fire setbacks

Fire Setback Enforced
1
Setback Notes

Pathways must be over supported roof structure meaning setbacks start at a load bearing wall

Structural & loads

Wind Speed
110
Wind Notes

Exposure Category B

Snow Load
0
Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Structural Notes

* This AHJ requires Roof Calcs - JH

Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
Line Side Taps,PV Breaker,Meter Adapter,Load Side Taps
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.91

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

Standard

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Plan Set Requirements

STANDARD

Electrical Diagram

For top feed panels, the sum of the breakers supplying power to the service panel busbarshall not exceed not exceed 120% of the bus bar rating. CEC 705.12 D 2 For center fed panels, the sum of the overcurrent devices shall not exceed 100%of the bus bar rating. CEC 705.12 D 7.

Custom Placards Required
1

Ground mount

Ground Mount Fencing Required
Mesh/Scrim