City of Palm Desert (CA)

California Authority Having Jurisdiction Solar permitting requirements

Spot something wrong?

These change with code cycles. If a requirement here is out of date or missing, tell us and we'll fix it.

Report a correction
NEC Code Version2023
Fire Code Version2018 Building Code
SolarAPP+ StatusTesting
Wet Stamps RequiredDigital Structural
Fire Setback EnforcedYes

Codes

NEC Code Version
2023
Fire Code Version
2018 Building Code
Code List

2025 CALIFORNIA BUILDING CODE

2025 CALIFORNIA ELECTRICAL CODE

2025 CALIFORNIA FIRE CODE

2025 CALIFORNIA PLUMBING CODE

2025 CALIFORNIA MECHANICAL CODE

2025 CALIFORNIA ENERGY CODE

2025 CALIFORNIA RESIDENTIAL CODE

2025 CALIFORNIA ADMINISTRATIVE CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Testing
Any SolarAPP+ Restrictions
Yes
SolarAPP+ Restrictions
MPU,Derate
How Many Plansets Required
3
Revision Required
Yes
Rough Inspection
Footing inspection for > 10kW
New Planset Required For Module Swap
No

Stamps

Ee Stamp Required On SLD
No
Wet Stamps Required
Digital Structural
Structural Calculations Required
Yes
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
Yes
Setback Notes

Standard

Structural & loads

Wind Speed
130
Wind Notes

Exposure Category C

Snow Load
0
Snow Load Notes

N/A

Reducible Snow Load Allowed
Yes
Max Attachment Spacing
96
Structural Notes

Standard

Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
Line Side Taps,Load Side Taps,Meter Adapter,PV Breaker
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.87

Battery / ESS

Unique Battery Placards Needed
No
ESS Notes

Standard

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Plan Set Requirements

If the MPU doubles the size of the main service panel, include a note that the overhead utility lines will be buried underground.

Site Notes

Include AC-kW value for new system NOT the CEC value

Electrical Diagram

Existing EV chargers must be shown on the Electrical Diagram

Custom Placards Required
No

Ground mount

Ground Mount Fencing Required
No
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the City of Palm Desert (CA) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.