City of Victorville (CA)

California Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2023
Fire Code Version2018 Building Code
SolarAPP+ StatusAdopted
Wet Stamps RequiredNone
Fire Setback Enforced1

Codes

NEC Code Version
2023
Fire Code Version
2018 Building Code
Code List

2025 CALIFORNIA BUILDING CODE

2025 CALIFORNIA ELECTRICAL CODE

2025 CALIFORNIA FIRE CODE

2025 CALIFORNIA PLUMBING CODE

2025 CALIFORNIA MECHANICAL CODE

2025 CALIFORNIA ENERGY CODE

2025 CALIFORNIA RESIDENTIAL CODE

2025 CALIFORNIA ADMINISTRATIVE CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Adopted
Any SolarAPP+ Restrictions
1
SolarAPP+ Restriction Notes

Building-integrated photovoltaics (BIPV).

SolarAPP+ Restrictions
Existing Systems,Trenching
How Many Plansets Required
3
Revision Required
1
Rough Inspection
None
New Planset Required For Module Swap
0

Stamps

Ee Stamp Required On SLD
Yes - 10kW+
Wet Stamps Required
None
Structural Calculations Required
Yes
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes

Existing systems must be included in the array roof coverage calculations to determine if modified setbacks can be used.

Structural & loads

Wind Speed
110
Wind Notes

Exposure Category C

Snow Load
5
Snow Load Notes

N/A

Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Structural Notes

Standard

Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates,Battery - Whole home backup,Battery - Partial Backup
Allowed POI
Line Side Taps,PV Breaker,Meter Adapter,Load Side Taps
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.91
BOS Restrictions

Standard

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

Provide electrical load calculations for Back-Up load panel and all circuits being moved to it.


ESS disconnect required within 6ft of BATTERY on same wall and not blocked by walls/gates/etc

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Electrical Diagram
  • AHJ is enforcing CEC 240.4(D) for small conductors. Need to include a note that states that CEC 240.4(D) will be followed, OR we need to demonstrate that terminal ratings are 75C for equipment.
Custom Placards Required
0

Ground mount

Ground Mount Fencing Required
No