County of Humboldt (CA)

California Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2023
Fire Code Version2018 Building Code
SolarAPP+ StatusAdopted
Wet Stamps RequiredNone
Fire Setback Enforced1

Codes

NEC Code Version
2023
Fire Code Version
2018 Building Code
Code List

2025 CALIFORNIA BUILDING CODE

2025 CALIFORNIA ELECTRICAL CODE

2025 CALIFORNIA FIRE CODE

2025 CALIFORNIA PLUMBING CODE

2025 CALIFORNIA MECHANICAL CODE

2025 CALIFORNIA ENERGY CODE

2025 CALIFORNIA RESIDENTIAL CODE

2025 CALIFORNIA ADMINISTRATIVE CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Adopted
Any SolarAPP+ Restrictions
1
SolarAPP+ Restrictions
Existing Systems,Trenching
How Many Plansets Required
3
Revision Required
1
Rough Inspection
None
New Planset Required For Module Swap
0

Stamps

Wet Stamps Required
None
Structural Calculations Required
No
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes

Standard

Structural & loads

Wind Speed
110
Wind Notes

Exposure Category B

Snow Load
0
Reducible Snow Load Allowed
1
Max Attachment Spacing
72
Structural Notes
AHJ requires structural calculations for manufactured homes.
Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
Meter Adapter,PV Breaker,Load Side Taps,Line Side Taps
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
1

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

Standard

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Plan Set Requirements

Trusses can have MAX attachments of 48 . AHJ will not allow 6' attachments for trusses even with stamps ** Rafters with 6' spans will qualify with Structural Criteria Check List, Trusses will not. If the project qualifies for structural criteria it may be used. If the project does not qualify we can request structural stamps - Does not apply to projects that qualify for solarapp

Attachment Detail

Per Structural Criteria (California Toolkit #5) Note #3: Trusses can have MAX attachments of 48". AHJ will not allow 6' attachments for trusses even with stamps **(PER a past project DCR 11/16/20)** Rafters with 6' spans will qualify with Structural Criteria Check List, Trusses will not. - Does not apply to projects that qualify for solarapp

Electrical Diagram
  • For MPUs, include the spec sheets of the new Service Panel.


  • Provide working clearances for PV inverters, batteries, disconnects and panelboards including 6โ€™6โ€ height. CEC 110.26(A)


  • Provide method of buss bar protection at main service panel per 705.12 or 705.13. If a PCS system will be used, please specify the busbars/circuits/power production sources to be monitored and/or controlled. Specify the max setting for monitored and controlled circuits of the power production sources. 
Custom Placards Required
1

Ground mount

Ground Mount Fencing Required
No
Ground Mount Notes

Include appropriate information from the plot plan on the site plan, such as septic and leach lines, waterways, easements, or pipelines. Reference the Plot Plan Checklist below for additional details.


Need to show at least a 20โ€™ setback from the edge of the road easement to the solar array.


Need to show the setback distance from ground mount solar array to property line.


For septic records:

Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the County of Humboldt (CA) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.