State of California - Manufactured Housing (HCD) (Sacramento) (CA)

California Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2023
Fire Code Version2018 Building Code
Wet Stamps RequiredDigital Structural
Fire Setback Enforced1

Codes

NEC Code Version
2023
Fire Code Version
2018 Building Code
Code List

2025 CALIFORNIA BUILDING CODE

2025 CALIFORNIA ELECTRICAL CODE

2025 CALIFORNIA FIRE CODE

2025 CALIFORNIA PLUMBING CODE

2025 CALIFORNIA MECHANICAL CODE

2025 CALIFORNIA ENERGY CODE

2025 CALIFORNIA RESIDENTIAL CODE

2025 CALIFORNIA ADMINISTRATIVE CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

How Many Plansets Required
3
Revision Required
1
Rough Inspection
None
New Planset Required For Module Swap
0

Stamps

Ee Stamp Required On SLD
Yes
Wet Stamps Required
Digital Structural
Structural Calculations Required
Yes
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes

Standard

Structural & loads

Wind Speed
110
Wind Notes

Exposure Category C

Snow Load
30
Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Structural Notes
  • PE letter to use verbiage provided in the "Sample Certification Letter" in the files section below.
  • Structural calcs required showing the added dead load weight of the panels does not affect the live load performance of the trusses.
  • Plan must be stamped and signed by a CA Licensed Design Professional.
Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
Load Side Taps,PV Breaker,Line Side Taps,Meter Adapter
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.91
BOS Restrictions

Standard

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

UL 9540a accepted

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Plan Set Requirements
  • LABEL ALL STRUCTURES ON SITE PLAN
Roof Plan

IDENTIFY THE PERIMETER OF THE MH FROM ADDITIONAL STRUCTURES

Attachment Detail
  • STANDARD 48 O.C. ATTACHMENTS STAGGERED FOR MOBILE/MANUFACTURED HOMES
  • CALLOUT 2X2 TRUSSES FOR MOBILE/MANUFACTURED HOMES & ECO 65 ROOF ATTACHMENTS
Electrical Diagram

Standard

Electrical Diagram Notes

Battery [Producer's storage device(s) will not cause the Host Load to exceed its normal peak demand. Normal peak demand is defined as the highest amount of power required from the Distribution System by Producer's complete facilities without the influence or use of the energy storage device(s).]

Custom Placards Required
1

Ground mount

Ground Mount Fencing Required
Mesh/Scrim
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the State of California - Manufactured Housing (HCD) (Sacramento) (CA) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.