City of Lakewood (CO)

Colorado Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2023
Fire Code Version2018 Building Code
SolarAPP+ StatusPiloting
Wet Stamps RequiredDigital Structural,Digital Electrical
Fire Setback Enforced1

Codes

NEC Code Version
2023
Fire Code Version
2018 Building Code
Code List

2021 INTERNATIONAL BUILDING CODE

2021 INTERNATIONAL RESIDENTIAL CODE

2021 INTERNATIONAL FUEL GAS CODE

2021 INTERNATIONAL MECHANICAL CODE

2021 INTERNATIONAL PLUMBING CODE

2021 INTERNATIONAL EXISTING BUILDING CODE

2021 INTERNATIONAL ENERGY CONSERVATION CODE

2021 INTERNATIONAL POOL AND SPA CODE

2021 INTERNATIONAL FUEL GAS CODE

2021 INTERNATIONAL PROPERTY MAINTENANCE CODE

2021 INTERNATIONAL FIRE CODE

2023 NATIONAL ELECTRICAL CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Piloting
Any SolarAPP+ Restrictions
1
SolarAPP+ Restrictions
Storage Systems,Existing Systems,Trenching,MPU
How Many Plansets Required
1
Revision Required
1
New Planset Required For Module Swap
0

Stamps

Ee Stamp Required On SLD
Yes - MSP 200A+
Wet Stamps Required
Digital Structural,Digital Electrical
Structural Calculations Required
Yes
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes

Standard

Structural & loads

Wind Speed
999
Wind Notes

Exposure category C


Note: 10,000 dividing line is Kipling in most, if not all, areas.

Single family/duplex homes are Risk Category II.


ULTIMATE WIND SPEED

Please include Wind Calculation in the Engineer Letter/Structural Calcs.

Risk Category I

Buildings and structures shall be 130 mph Vult for all structures east of the 10,000 West block and 155mph Vult for all other structures in all other locations.

Risk Category II

Buildings and structures shall be 138 mph Vult for all structures east of the 10,000 West block and 166 mph Vult for all other structures in all other locations.

Risk Category III and IV

Buildings and structures shall be 148 mph Vult for all structures east of the 10,000 West block and 178 mph Vult for all other structures in all other locations.

Snow Load
30
Snow Load Notes

Roof snow load: 30 PSF. Engineering letter and engineer calculations must use a minimum roof snow load of 30 psf per 2021 IRC Table R301.2 and the Lakewood Amendments.


Per recent AHJ kickbacks the D+F (psf) must be 33 psf. City of Lakewood states that any value under 30 psf is impossible if we are using a 30 psf non-reducible snow load.

Reducible Snow Load Allowed
0
Max Attachment Spacing
96
Structural Notes

The City of Lakewood is located in a "Special Wind Region." See Wind Notes field for more information

Minimum Ground On Roof
#6

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
Line Side Taps,Load Side Taps,Meter Adapter,PV Breaker
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.96

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

No published information about battery placement. Mays, Jovan. AHJ: City of Lakewood (CO). Equipment in garage no longer required. [DCR 122820] Battery and inverter are supposed to be inside the garage. [DCR 083120] PM required for projects over 10kW-DC. Call out STEEL PRODUCTION METER, 120/240V 3-WIRE . Install a brass tag that says PV PROD and the house number but not the whole address. For example, if the address is 6200 West Mexico Avenue, the brass tag should say PV PROD 6200 .

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Plan Set Requirements

Structural connections must be directly connected to the roof framing through not more than one layer of asphalt shingles. Special connection details will be considered by the Building Official as an alternate connection method. Connections cannot be made through tile or wood shingle roofs. The roof connection must be flashed with an approved system. Connection to the roof sheathing only is not allowed. Structural connections must be too solid framing. There must be no fewer than 2 connections per solar panel. The panel systems cannot obstruct any plumbing or mechanical vents. Provide spec sheets for flashings, mounting system grounding and bonding, and panel compatibility sheet. * Add SFM railless UL2703 cert for SFM projects to plans.

Roof Plan

DO NOT COVER ANY TYPE OF ROOF VENTS WITH PV MODULES STRUCTURAL CONNECTIONS MUST BE DIRECTLY CONNECTED TO THE ROOF FRAMING THROUGH NOT MORE THAN ONE LAYER OF ASPHALT SHINGLES. SPECIAL CONNECTION DETAILS WILL BE CONSIDERED BY THE BUILDING OFFICIAL AS AN ALTERNATE CONNECTION METHOD. CONNECTIONS CANNOT BE MADE THROUGH TILE OR WOOD SHINGLE ROOFS. THE ROOF CONNECTION MUST BE FLASHED WITH AN APPROVED SYSTEM. CONNECTION TO THE ROOF SHEATHING ONLY IS NOT ALLOWED. STRUCTURAL CONNECTIONS MUST BE TOO SOLID FRAMING. THERE MUST BE NO FEWER THAN 2 CONNECTIONS PER SOLAR PANEL. THE PANEL SYSTEMS CANNOT OBSTRUCT ANY PLUMBING OR MECHANICAL VENTS.

Attachment Detail


Electrical Diagram

Standard

Custom Placards Required
0

Ground mount

Ground Mount Fencing Required
No
Ground Mount Notes

Soil Class: Clay For ground-mounted solar systems you must also provide:  Plot Plan was drawn to 1” = 30’ or larger standard engineering scale. See page 3 of this handout for an example of the required plot plan.  You may draw a plot plan or you may use an Improvement Location Certificate (ILC) as your Plot Plan submittal. Make a copy of the ILC and add the required information. Draw the proposed solar panel location on the copy of the ILC using the same scale as the original.  Include north arrow and scale used.  Provide the property address and names of all adjacent streets.  Show all property lines and easements with dimensions.  Show the footprint of the existing home and the new solar panels.  Show all existing accessory buildings and label type and dimensions (e.g. 10’ x 12’ shed).  Show all walks, drives, and patios.  Provide dimensions on all sides from the new solar panels to property lines and other structures on the lot. Structural analysis of the existing roof and calculations for the new installation must be performed by a registered Colorado Professional Engineer when:  The new panel system exceeds 3.5 pounds per square foot  The existing roof has multiple layers of roof covering  Panels are not installed parallel to the roof surface (they are installed at a slope that is not parallel to the existing roof)  The system is installed greater than 12” above the existing roof surface  The roof structure is a flat roof system  The system is to be installed on a commercial building.

Ground Mount Requires Soil Sample
Soil Study
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the City of Lakewood (CO) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.