Codes
- NEC Code Version
- 2020
- Fire Code Version
- 2018 Building Code
- Code List
2023 8TH EDITION FLORIDA BUILDING CODE: BUILDING
2023 8TH EDITION FLORIDA BUILDING CODE: RESIDENTIAL
2023 8TH EDITION FLORIDA BUILDING CODE: MECHANICAL
2023 8TH EDITION FLORIDA BUILDING CODE: PLUMBING
2023 8TH EDITION FLORIDA BUILDING CODE: FUEL GAS
2023 8TH EDITION FLORIDA BUILDING CODE: ENERGY CONSERVATION
2023 8TH EDITION FLORIDA BUILDING CODE: EXISTING BUILDING
2023 8TH EDITION FLORIDA BUILDING CODE: ACCESSIBILITY
2023 8TH EDITION FLORIDA FIRE PREVENTION CODE (NFPA)
2020 NATIONAL ELECTRIC CODE (NEC)
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- How Many Plansets Required
- 2
- Revision Required
- 1
- Rough Inspection
- Rough Electrical
- New Planset Required For Module Swap
- 1
Stamps
- Ee Stamp Required On SLD
- Yes
- Wet Stamps Required
- Wet Structural,Wet Electrical
- Structural Calculations Required
- Yes
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 0
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 175
- Wind Notes
Exposure Category C
- Snow Load
- 0
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 48
- Structural Notes
Engineers cannot be changed during the project
- Minimum Ground On Roof
- #10
Electrical
- AC Disconnect Required
- Yes
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Line Side Taps,PV Breaker,Load Side Taps
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Standard
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Plan Set Requirements
APPROVED PLANSET UPLOADED FOR CORRECT REFERENCE
STRUCTURAL WIND DESIGN MUST COMPLY WITH SECTION 1620, HVHZ PROVISIONS OF THE FBC 7th EDITION (2020), USING WIND SPEED OF 175 MPH, AND EXPOSURE C CATEGORY FOR MIAMI DADE-COUNTY, FLORIDA.
- Cover Page Notes
THIS SYSTEM DESIGNED WITH:
WIND SPEED: 175
WIND EXPOSURE: C
CATEGORY II
3 SECOND GUST
- Roof Plan
Roof pressure zones required to be calculated or presented correctly on plans PV modules, Racking, connection, and Stand-offs shall be rated for the wind pressure zones they are installed in
- Custom Placards Required
- 0
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim