County of Collier (FL)
Codes
- NEC Code Version
- 2020
- Fire Code Version
- 2018 Building Code
- Code List
2023 8TH EDITION FLORIDA BUILDING CODE: BUILDING
2023 8TH EDITION FLORIDA BUILDING CODE: RESIDENTIAL
2023 8TH EDITION FLORIDA BUILDING CODE: MECHANICAL
2023 8TH EDITION FLORIDA BUILDING CODE: PLUMBING
2023 8TH EDITION FLORIDA BUILDING CODE: FUEL GAS
2023 8TH EDITION FLORIDA BUILDING CODE: ENERGY CONSERVATION
2023 8TH EDITION FLORIDA BUILDING CODE: EXISTING BUILDING
2023 8TH EDITION FLORIDA BUILDING CODE: ACCESSIBILITY
2023 8TH EDITION FLORIDA FIRE PREVENTION CODE (NFPA)
2020 NATIONAL ELECTRIC CODE (NEC)
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- SolarAPP+ Status
- Not accepted
- Any SolarAPP+ Restrictions
- 1
- SolarAPP+ Restrictions
- MPU,Derate
- Revision Required
- 1
- Rough Inspection
- None
- New Planset Required For Module Swap
- 0
Stamps
- Ee Stamp Required On SLD
- Yes
- Wet Stamps Required
- Digital Structural,Digital Electrical
- Structural Calculations Required
- Yes
- Ee Stamp Notes
FL statute letter required
Digitally Verified Signature
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Structural & loads
- Wind Speed
- 170
- Wind Notes
Exposure Category C
- Snow Load
- 0
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 48
- Structural Notes
Digitally Verified Signature
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Line Side Taps,Load Side Taps,PV Breaker
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.96
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Standard
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Plan Set Requirements
- Roof Plan Notes
All Jobs [Photovoltaic panels and modules shall be listed and labeled in accordance with UL 1703 per FBC-R 324.3.1, or with both UL 61730-1 and UL 61730-2 per 2021 IRC 324.3.1.]
- Electrical Diagram Notes
All Jobs [Service panels will be elevated to the height of the existing electric panels, the finished floor elevation, or Base Flood Elevation plus one foot]
- Label Page
FLORIDA 2020 CAD BLOCK
- Custom Placards Required
- 0
- Non Standard Planset Requirements
- BOS Elevation
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim
- Ground Mount Notes
Ground-Mount / Impervious Area Requirements
- Any new structure adding 400 sq. ft. or more of impervious area requires a Certified Site Plan at the time of submittal.
Certified Site Plan Requirements
- Must be prepared, signed, and sealed by a licensed Florida:
- Professional Surveyor & Mapper
- Architect, or
- Engineer
- Professional must be familiar with County zoning and setback requirements.
Certified Site Plan Must Include
- All existing and proposed structures
- Property lines
- Setbacks to the proposed new structure
- Separation distances between structures
- All easements
- Water bodies (if applicable)
- Crown of road elevation
- FEMA Base Flood Elevation (BFE)