Codes
- NEC Code Version
- 2020
- Fire Code Version
- 2018 Building Code
- Code List
2023 8TH EDITION FLORIDA BUILDING CODE
2023 8TH EDITION FLORIDA RESIDENTIAL CODE
2023 8TH EDITION FLORIDA MECHANICAL CODE
2023 8TH EDITION FLORIDA PLUMBING CODE
2023 8TH EDITION FLORIDA FUEL GAS CODE
2023 8TH EDITION FLORIDA ENERGY CONSERVATION CODE
2023 8TH EDITION FLORIDA EXISTING BUILDING CODE
2023 8TH EDITION FLORIDA ACCESSIBILITY CODE
2023 8TH EDITION FLORIDA FIRE PREVENTION CODE
2020 NATIONAL ELECTRICAL CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- SolarAPP+ Status
- Not accepted
- Any SolarAPP+ Restrictions
- 1
- How Many Plansets Required
- 1
- Revision Required
- 1
- Rough Inspection
- None
- New Planset Required For Module Swap
- 1
Stamps
- Ee Stamp Required On SLD
- Yes
- Wet Stamps Required
- Digital Structural,Digital Electrical
- Structural Calculations Required
- Yes
- Ee Stamp Notes
Signed, stamped and Digitally Verified Signature
- Stamp Location On Plans
- Top Right
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 150
- Wind Notes
Exposure Type C
- Snow Load
- 0
- Reducible Snow Load Allowed
- 0
- Max Attachment Spacing
- 48
- Structural Notes
Installation on Mobile homes is not allowed in this AHJ. PE Requirements; SE & EE digital stamps and signatures on all PV pages, FL Statute & PE Letter / Calcs. Every PV page that is stamped also needs to be digitally signed
Digitally Verified Signature
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Line Side Taps,PV Breaker,Load Side Taps,Meter Adapter
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.96
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
- ess must be under own disconnect, gen disco not allowed
- DC Coupled batteries do not need a DC disconnect
- Separate ESS Disconnect Required
- ESS Disconnect,No
- ESS Elevation Detail Required
- No
Plan set
- Plan Set Requirements
Installation on Mobile homes is not allowed in this AHJ.
- Roof Plan Notes
All Jobs [Layout subject to change]
- Electrical Diagram
Standard
- Electrical Diagram Notes
All Jobs [Interconnection Method subject to change]
- Custom Placards Required
- 1
- Placards Notes
- If the utility is TECO, they have strict placard requirements. Please refer to the TECO - Tampa Electric Company database for placard requirements.
- If more than one (1) disconnect, the placards will also include 1of2, 2of 2, etc.
- If the electric meter is more than 6 feet from the disconnect, a custom placard for the meter will be required: "On Site Generation Utility Disconnect Located xx Feet to the Left/Right Of Utility Meter" will be required
- Meter placard will also be required if the equipment is separated by a fence.
- Meter placard will also be required if the meter and disconnect are on opposite walls no matter if there is no fence or if they are under 6 ft apart
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim
- Ground Mount Notes
Fencing required.
- Setback Back Yard
- 15