County of Monroe (IL)

Illinois Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2005
Fire Code Version2015 Building Code
Wet Stamps RequiredDigital Structural
Fire Setback Enforced0

Codes

NEC Code Version
2005
Fire Code Version
2015 Building Code
Code List

2005 NATIONAL ELECTRIC CODE

2006 INTERNATIONAL BUILDING CODE

IEBC Accepted
0
ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

Revision Required
1
Rough Inspection
None
New Planset Required For Module Swap
0

Stamps

Ee Stamp Required On SLD
No
Wet Stamps Required
Digital Structural
Structural Calculations Required
Yes
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
0
Setback Notes

Standard

Structural & loads

Wind Speed
90
Snow Load
20
Reducible Snow Load Allowed
1
Structural Notes

SE Stamps/Calcs required

Minimum Ground On Roof
#10

Electrical

AC Disconnect Required
Yes
Allowed POI
PV Breaker,Line Side Taps,Load Side Taps,Meter Adapter
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.91
BOS Restrictions


Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

AHJ doesn’t allow SEEB batteries to be installed outside, only Tesla batteries, due to SEEB having operational temperatures of 14 deg. while Tesla's is -4 deg.

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Electrical Diagram
  • The Nema 3R disconnect switch should be adjacent to the electric meter and accessible to the servicing utility company.
  • The switch must be fusible, minimum size 100 Amp, single phase or three phase and rated for service voltage.
  • The switch must be securely fastened to the building structure, have a visible open gap between the switch contacts, knife-blade type.
  • Fusible safety switch must include a label staô€†źng voltage and amperage of solar system and all addiô€†źonal labels required.
Label Page
  • Plaques must be either attached to the AC Generation Safety Disconnect or located next to the disconnect. Plaques are not allowed to be mechanically attached to the safety switch with screws, pop rivets, or similar means, as this would compromise the UL rating.
  • Plaque must be a minimum of 5” x 7” in size.
  • Wording for the plaque at the safety disconnect switch must state: “CAUTION: Multiple Sources of Power - Lockable AC Generation Source Disconnect.”
  • If the disconnect is within 10 feet and within sight of the meter, the signage must state: “CAUTION: Multiple Sources of Power - Lockable AC Generation Source Disconnect available for Isolation from Utility.”
  • Plaque must be a two-ply or three-ply, non-conductive plastic engraved plate that is weatherproof and UV resistant.
  • All solar raceways/conduit installed with DC and AC conductors must be labeled every 10 feet minimum as:
  • “Warning: Photovoltaic Power Source.”
Custom Placards Required
0

Ground mount

Ground Mount Fencing Required
Mesh/Scrim