Codes
- NEC Code Version
- 2020
- Fire Code Version
- 2018 Building Code
- Code List
2021 INTERNATIONAL BUILDING CODE
2021 INTERNATIONAL RESIDENTIAL CODE
2021 INTERNATIONAL FIRE CODE
2021 INTERNATIONAL ENERGY CONSERVATION CODE
2021 INTERNATIONAL EXISTING BUILDING CODE
2021 INTERNATIONAL FUEL GAS CODE
2021 INTERNATIONAL MECHANICAL CODE
2021 INTERNATIONAL PLUMBING CODE
2020 NATIONAL ELECTRICAL CODE (NEC)
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- SolarAPP+ Status
- Targeted
- Any SolarAPP+ Restrictions
- 1
- SolarAPP+ Restrictions
- MPU,Derate
- How Many Plansets Required
- 1
- Revision Required
- 0
- New Planset Required For Module Swap
- 0
Stamps
- Wet Stamps Required
- Digital Structural
- Structural Calculations Required
- Yes
- Stamp Location On Plans
- Top Right
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 115
- Wind Notes
Exposure Category B
- Snow Load
- 25
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Structural Notes
Standard
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- PV Breaker,Load Side Taps,Meter Adapter,Line Side Taps
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
- BOS Restrictions
If there is to be a fused disco inside, use a flush-mounted breaker housing instead of a surface-mounted knife-blade switch. Former is aesthetically pleasing. Latter is not. If lineside tap they require a fused disconnect to be installed inside the home with a non fused disconnect outside.
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Standard
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Plan Set Requirements
If there is to be a fused disco inside, use a flush-mounted load center with breaker instead of a surface-mounted knife-blade switch. Former is aesthetically pleasing. Latter is not. Check service cable to see if frayed If so will require replacement to pass inspection If lineside tap they require a fused disconnect to be installed inside the home with a non fused disconnect outside. If finish basement please design using flush mount load center.
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim