New Hampshire Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2020
Fire Code Version2015 Building Code
Fire Setback Enforced1

Codes

NEC Code Version
2020
Fire Code Version
2015 Building Code
Code List

2021 NH STATE BUILDING CODE

2021 NH STATE FIRE CODE

2021 INTERNATIONAL BUILDING CODE

2021 INTERNATIONAL RESIDENTIAL CODE

2021 INTERNATIONAL MECHANICAL CODE

2021 INTERNATIONAL PLUMBING CODE

2018 INTERNATIONAL ENERGY CONSERVATION CODE

2021 INTERNATIONAL EXISTING BUILDING CODE

2021 INTERNATIONAL SWIMMING POOL AND SPA CODE

2021 NFPA 1, FIRE CODE AS AMENDED BY SAF-FMO 300

2021 NFPA 101 LIFE SAFETY CODE AS AMENDED BY SAF-FMO 300

2020 NATIONAL ELECTRICAL CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

How Many Plansets Required
1
Revision Required
0
New Planset Required For Module Swap
0

Stamps

Structural Calculations Required
No

Fire setbacks

Fire Setback Enforced
1
Setback Notes

3 FOOT OFFSET REQUIRED

Structural & loads

Wind Speed
90
Snow Load
85
Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
Line Side Taps,Load Side Taps,Meter Adapter,PV Breaker
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.91

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

Standard

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Cover Page Notes


Site Notes

Add note

[This certification excludes evaluation of the following components:

  1. The structure to support the loads imposed on the building by the array; including but not limited to: strength and deflection of structural framing members, fastening and/or strength of roofing materials, and/or the effects of snow accumulation on the structure.
  2. The attachment of the Solar Mount racking to the existing structure.
  3. The capacity of the solar module frame to resist the loads

This requires additional knowledge of the building and is outside the scope of the certification of this racking system.]

Ground mount

Ground Mount Fencing Required
Mesh/Scrim