City of Orange Township (Essex County) (NJ)

New Jersey Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2020
Fire Code Version2018 Building Code
Wet Stamps RequiredWet Structural
Fire Setback Enforced1

Codes

NEC Code Version
2020
Fire Code Version
2018 Building Code
Code List

2021 INTERNATIONAL BUILDING CODE

2021 INTERNATIONAL RESIDENTIAL CODE

2021 INTERNATIONAL FIRE CODE

2021 INTERNATIONAL ENERGY CONSERVATION CODE

2021 INTERNATIONAL EXISTING BUILDING CODE

2021 INTERNATIONAL FUEL GAS CODE

2021 INTERNATIONAL MECHANICAL CODE

2021 INTERNATIONAL PLUMBING CODE

2020 NATIONAL ELECTRICAL CODE

ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

How Many Plansets Required
3
Revision Required
0
New Planset Required For Module Swap
0

Stamps

Ee Stamp Required On SLD
No
Wet Stamps Required
Wet Structural
Structural Calculations Required
Yes
Stamp Location On Plans
Unspecified
Date On Stamps
Expiration Date

Fire setbacks

Fire Setback Enforced
1
Setback Notes

Standard

Structural & loads

Wind Speed
115
Wind Notes

Exposure Category B

Snow Load
25
Reducible Snow Load Allowed
1
Max Attachment Spacing
96
Structural Notes

*****SEE FILES SECTION BELOW FOR AHJ HISTORIC COMMISSION DESIGN GUIDELINES***** ** ** **Raised seal required for (3) plans.**

Minimum Ground On Roof
#10

Electrical

Electrical Load Calcs Required
Derates
Allowed POI
Line Side Taps,Meter Adapter,PV Breaker,Load Side Taps
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.91

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

Standard

Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
No

Plan set

Plan Set Requirements

If the home is in a historical district, specific restrictions will be applied. Steps to determine if the home is in a historic district: 1. Pull the home's block and lot number from the property record from this site: 2. The block and lot will appear on the right once the address is searched. 3. Open the PDF Historic District Properties in the files below and search for the block and lot number from the list of properties. If the property appears on the list, historic preservation restrictions will apply. Design requirements for projects in a historical district: Panels cannot be visible from the street. Include photographs of the site where solar will be installed, showing relevant elevations and how solar will not be seen from the street. The photos must be taken from ground level from the front of the property. Any plants or trees that will be removed due to the installation will need to be called out on the plans See information in Files.

Electrical Diagram

If lineside tap (LST), then a Hoffman Tap Box (junction box) is required.

Electrical Diagram Notes


Custom Placards Required
0
Non Standard Planset Requirements
BOS Elevation

Ground mount

Ground Mount Fencing Required
Mesh/Scrim
Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the City of Orange Township (Essex County) (NJ) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.