Township of Kingwood (Hunterdon County) (NJ)
Codes
- NEC Code Version
- 2020
- Fire Code Version
- 2018 Building Code
- Code List
2021 INTERNATIONAL BUILDING CODE
2021 INTERNATIONAL RESIDENTIAL CODE
2021 INTERNATIONAL FIRE CODE
2021 INTERNATIONAL ENERGY CONSERVATION CODE
2021 INTERNATIONAL EXISTING BUILDING CODE
2021 INTERNATIONAL FUEL GAS CODE
2021 INTERNATIONAL MECHANICAL CODE
2021 INTERNATIONAL PLUMBING CODE
2020 NATIONAL ELECTRICAL CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- How Many Plansets Required
- 1
- Revision Required
- 0
- New Planset Required For Module Swap
- 0
Stamps
- Ee Stamp Required On SLD
- No
- Wet Stamps Required
- Wet Structural
- Structural Calculations Required
- Yes
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 115
- Wind Notes
Exposure Category B
- Snow Load
- 30
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Structural Notes
**Digital seal accepted for plans.** **Applications are submitted online.**
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Line Side Taps,Load Side Taps,PV Breaker,Meter Adapter
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.96
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Standard
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Site
Must call out all fences and gates on property. Label if locked or not.
- Roof Plan
**AHJ is VERY STRICT with fire setbacks.** **\- 4' from ridges and rakes, and 2' on each side of hips and valleys**
- Roof Plan Notes
All conduit extending between solar or PV panel arrays and inverters and transformers shall be marked every 10' to indicate electrical danger to firefighters and EMT personnel in the event conduit is accidentally or must be intentionally cut as part of an emergency response.
- Electrical Diagram
Call out inverter having integrated rapid shutdown per 690.12
If lineside tap (LST), then a Hoffman Tap Box (junction box) is required.
- Electrical Diagram Notes
- Custom Placards Required
- 0
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim