County of Clark (NV)

Nevada Authority Having Jurisdiction Solar permitting requirements
NEC Code Version2017
Fire Code Version2018 Building Code
SolarAPP+ StatusTargeted
Wet Stamps RequiredDigital Structural,Digital Electrical
Fire Setback Enforced1

Codes

NEC Code Version
2017
Fire Code Version
2018 Building Code
Code List

2018 UNIFORM PLUMBING CODE

2018 UNIFORM MECHANICAL CODE

2018 INTERNATIONAL SWIMMING POOL AND SPA CODE

2018 INTERNATIONAL RESIDENTIAL CODE

2018 INTERNATIONAL EXISTING BUILDING CODE

2021 INTERNATIONAL ENERGY CONSERVATION CODE

2018 INTERNATIONAL BUILDING CODE

2018 BUILDING ADMINISTRATIVE CODE OF CLARK COUNTY

2017 NATIONAL ELECTRICAL CODE

2018 INTERNATIONAL FIRE CODE

IEBC Accepted
1
ASCE Code Specification
ASCE 7-16

SolarAPP+ & submittal

SolarAPP+ Status
Targeted
Any SolarAPP+ Restrictions
1
SolarAPP+ Restrictions
MPU,Derate
How Many Plansets Required
Other (See Submission Notes)
Revision Required
1
Rough Inspection
None
New Planset Required For Module Swap
0

Stamps

Ee Stamp Required On SLD
Yes
Wet Stamps Required
Digital Structural,Digital Electrical
Structural Calculations Required
Yes
Ee Stamp Notes

Structural & Electrical Engineering Stamping Requirements

  • Digital Signature of Structural Engineer must show metadata.
  • Remove staff’s signature from all pages before stamping.
  • Plans must be stamped and digitally signed by both Electrical and Structural Engineers.
  • Mounting Equipment spec sheets must have SE Stamps.

Plans must include

  • Engineer’s electronic stamp on every page.
  • Engineer’s electronic signature on every page.
  • Engineer’s digital signature on the first page.
  • Expiration date of the licensee’s license (2020 Blue Book, #1b pg. 19).
  • Digital signature guide: Digital Signature Guide.

Stamping & Signature Rules

  • Any changes to submitted plans require new stamps.
  • EE Stamp required on Load Calcs and applicable pages (SLD, TLD, Conductor Calculations, Service Panel Photos, Label/Placards pages).
  • Stamps must show date stamped, expiration, and verifiable valid digital PDF signatures.
  • Nevada Board of Professional Engineers (NRS 625.610) requires each design professional to include:
  • Digital signature on the first page of each discipline.
  • Stamp, expiration date, and date of signature on each sheet.
  • Reference guide: Digital Signature Guide.
  • Digitally Verified Signature required for EE & SE stamps, showing metadata next to the stamp.
  • Refer to “dated stamp, digitally signed” in the files section for guidance.

Digitally Verified Signature

Stamp Location On Plans
Unspecified
Date On Stamps
Date Plans are Stamped

Fire setbacks

Fire Setback Enforced
1
Ridge Setback
36
Setback Notes

Standard


For PV arrays located on both sides of a ridge, at least one side of the ridge should maintain the 36 inch clearance regardless of area coverage (Clark County Policy and Procedure BP-DI-206)

See Guideline Attachment

Structural & loads

Wind Speed
115
Wind Notes

Exposure Category B

Snow Load
999
Snow Load Notes

< 2000 FT = 0 PSF

< 3600 FT = 5 PSF

< 4500 FT = 10 PSFT

< 6000 FT = 15 PSF

6000 FT ELEVATION = 40 PSF

7000 FT ELEVATION = 100 PSF

Reducible Snow Load Allowed
1
Max Attachment Spacing
48
Structural Notes

Any changes to plans will require new stamps.

PE Requirements:

Digital signature and stamp to show metadata next to stamp.

The Nevada Board of Professional Engineers (NRS 625.610) requires that each design professional add their digital signature to the first page of each discipline in combination with a stamp, expiration date, and date of signature on each sheet. The digital signature guide can be found here: https://nvbpels.org/wp-content/uploads/2020/11/Digital-Signature-Guide-FINAL.pdf Please refer to page 4 of this document, which shows an example of the format needed for the digital signature. The text that begins with "digitally signed by..." in the example image is required as part of the digital signature.

Solar Photovoltaic Structural Requirements BP-DI-206, Effective 09-01-20.pdf:

https://files.clarkcountynv.gov/clarknv/Building%20&%20Fire%20Prevention/Policies%20(PnPs)/2021/Solar%20Photovoltaic%20Structural%20Requirements%20BP-DI-206,%20Effective%2009-01-20.pdf?t=1612395087787&t=1612395087787

Minimum Ground On Roof
#8

Electrical

Electrical Load Calcs Required
Derates,MPUs
Allowed POI
PV Breaker
Panel Schedule Required
Partial Home Backup
Temperature Rating
90
De Rating Ampacity
0.87

Battery / ESS

Unique Battery Placards Needed
0
ESS Notes

Interior ESS:

  • Provide a layout to scale of the inside of the structure showing the location, access, clearances, egress and protection of the battery storage system and its components. CCBAC 22.02.235 and NEC 706.10 (A thru E).
  • Show on the plans the ventilation for the off gassing of the batteries and upload the manufactures installation instructions for the installation of the batteries. CCBAC 22.02.235 and NEC 706.10 (A thru E)
  • Show on the plans the illumination requirements for the battery storage system. CCBAC 22.02.235 and NEC 706.10 (A thru E)
  • Luminaires shall not be controlled by the automatic garage door opener only. NEC706.10(E).
Separate ESS Disconnect Required
ESS Disconnect
ESS Elevation Detail Required
Yes - with dimensions

Plan set

Plan Set Requirements

ALL PROJECTS:

  • At CR review if home is identified as a manufactured home, submit a ticket to the permitting team to have the AHJ updated to MHD
  • Must note "NOT FOR PLAN REVIEW" in red text on Optimizer Chart, Safety Plan, & Job Hazard Analysis pages. AHJ no longer requires these pages to be removed from the plan set if we add this note. 
  • When quoting module rating, show CEC rating, not PTC rating.
  • PV plans do not need stamping unless over 15 KW
  • Remove Greg's signature from the pages being stamped. His signature is needed on any pages that will not be stamped. 
  • When requesting stamping please make sure the engineers have their stamp digitally signed showing meta data next to stamp. refer to "dated stamp, digitally signed" in the files section

MPU Projects:

  • MPUs are permitted separately, and will require a dedicated plan set for MPU only:
  • MPU Plan Set NEEDS staff's signature, and does not need to be stamped
  • Complete MPU Plans, not mentioning PV at all:
  • Cover page
  • Site plan showing existing service location (Include Cross Steet) and where new service will be, if not expected to change, include a note: MSP expected to keep same location
  • Show existing and new panel size on plans (EX: Existing panel is 100A, to be upgraded to 225A)
  • SLD -labeling service conductors, & feeder conductors sizing
  • MSP Spec Sheet
  • Load calculates with existing AND future new loads
  • An example of an approved MPU plan set has been added to the files section for reference

Sub Panel Projects:

  • Sub Panels are permitted separately, and will require a dedicated plan set for Sub Panel only:
  • Sub Panel Plan Set NEEDS staff's signature, and does not need to be stamped
  • Complete Sub Panel Plans, not mentioning PV at all:
  • Cover page
  • Site plan showing existing Sub Panel's location
  • SLD -labeling service conductors, show MSP and must show all load & feeder conductors sizing
  • Sub Panel Spec Sheet
  • Load calculates with existing AND future new loads

Battery Projects:

  • Batteries are permitted separately, and will require a dedicated plan set for Battery only:
  • Battery Plan Set NEEDS staff's signature, and does not need to be stamped
  • Complete Battery Plans, not mentioning PV at all:
  • Cover page
  • Site plan showing Battery's location
  • SLD -labeling service conductors, & feeder conductors sizing
  • Battery Spec Sheet
  • Load calculates with existing AND future new loads


EV Charger Projects:

  • EV Chargers are permitted separately, and will require a dedicated plan set for EV Charger only:
  • The EV charger shall comply with 2017 NEC Art.625.52

  • Complete EV Charger Plans, not mentioning PV at all:
  • Site plan showing UM, MSP and new EV charger location
  • in the title box Indicate the description of work.
  • EV charger spec sheet

New AHJ Feedback EV charger plans to include:

1. Points of connection to utilities. NEC 230 (or Panel for remodels).

2. Show Service Location (230, size and Grounding. NEC 250

3. Single line diagrams. NEC 215.5

4. Load calculations. NEC 215.5

5. Panel location and schedules. 408.4

6. Site Plan and Floor Plan and identify the rooms. IBC 107.2.6

7. Wiring sizes (210) and circuiting. (Table 310.15.16.)

Cover Page


ALL of the following information is required for the scope of work on the cover sheet.

1. Size of the system - DC size and AC size (automatically included)

2. Modules - quantity, manufacturer, and model number (automatically included)

3. Inverters/Microinverters - quantity, manufacturer, and model number (automatically included)

4. Combiners - quantity, manufacturer, and model number OR load center (manual addition by designer)

5. Energy Storage System (ESS) - quantity, manufacturer, and model number, if any (automatically included)

6. Main panel upgrade or Derate (manual addition by designer)

7. Sub-Panels, load centers (manual addition by designer)

8. Location - Ground or Roof Mount (manual addition by designer)

9. Size of exiting PV system (manual addition by designer)

10.Provide "yes or no" answers for if the system will have a Battery, MPU, or Sub panel, touching up on all 3. EX-

Battery: No

MPU: Yes

Sub Panel: No

Cover Page Notes

Digital Signature of Structural Engineer showing meta data.


Please Remove staff's signature from all pages, then have Plans Stamped and Digitally Signed by Electrical and Structural Engineers



Must note "NOT FOR PLAN REVIEW" in red text on Optimizer Chart, Safety Plan, & Job Hazard Analysis pages.


Please add the following to the Title Box


  • Combiners or load center info - quantity, manufacturer, and model number
  •  Location - Ground or Roof Mount
  • Provide "yes or no" answers for if the system will have a Battery, MPU, or Sub panel, touching up on all 3. EX-Battery: No, MPU: no, Sub Panel: No
Site

Properties that are more units than a duplex are considered Commercial Properties. For any considered Commercial Property we will need to have adjust plans to show the following:

  • 4 ft Set Backs on all edges of the roof and from the ridge
  • Please Remove staff's signature from all pages, then have Plans Stamped and Digitally Signed by Electrical and Structural Engineers
  • Mounting Equipment spec sheets need SE Stamping as well, including Eco System Engineer letter
  • Structural Calculations and PE Letter needed
  • Measurements to the panels from all 4 directions of the roof
  • No QR codes allowed
Roof Plan

Existing Systems:

Add lines and arrows to the Existing modules on all pertaining arrays, including Placard Page. 

Duplex/multi-unit structures:

When there is not a parapet separating each tenant's roof, provide a 4 ft minimum separation clearance dimension from the adjacent tenant's exterior wall and roof surface to the solar panels. 

Shared Roof EX Townhomes/Condos

WHEN WE HAVE PANELS ON BOTH SIDES OF A SHARING RIDGE, AT LEAST ONE SIDE MUST HAVE 3 FT SET BACK REGARDLESS OF SYSTEM SIZE.

Attachment Detail

Embedment diagrams must specifically state "5/16" STAINLESS STEEL LAG BOLT OR STRUCTURAL SCREW WITH 2-1/2" MINIMUM ATTACHMENT DEPTH AND FLAT WASHER"

Attachment Detail Notes

All Jobs [Maximum attachment span 4ft]

Electrical Diagram
  • Load Calcs are required for De-rate or MPU. Load calcs page must have the same title block as the rest of the plan pages.
  • MPU load calcs must include new additional loads
  • Call out the wire size between the utility meter and the MSP
Custom Placards Required
1
Placards Notes

hard plastic placards only

Non Standard Revision Requirements

Plans will be rejected if you do not follow these instructions and items below.

1. On the top of the narrative document list the revision number BDxx-xxxxx-R00x (this is the Permit number [Ex: BD22-37660] then "-R00" and whichever revision number the narrative is for [Ex: BD22-37660-R003] if it were the 3rd revision requested)

2. Identify in the narrative the pages that have changes in a list format. Each drawing, sheet or page should be a separate line item. Next to each page number, describe the changes for that page in detail. Do not use “general” statements.

3. The revised drawing, sheet or pages shall have a cloud around the area(s) which were changed, and a numbered delta symbol used to identify the submitted revision. Clouds around the entire drawing will not be accepted.

Ground mount

Ground Mount Fencing Required
Yes
Ground Mount Notes

If the HO is getting a Ground Mount system we will need to pull two separate permits one for the roof-top solar and the other one for the GM permit in person. (Not online)

Compiled from public records, 2026. Requirements change with code cycles and local amendments. Verify with the County of Clark (NV) building department before you rely on this, and treat it as a research head start, not a ruling. Getting quotes? Run them through the quote checker first.