City of Trotwood (OH)
NEC Code Version2023
Fire Code Version2018 Building Code
Wet Stamps RequiredDigital Structural
Fire Setback Enforced1
Codes
- NEC Code Version
- 2023
- Fire Code Version
- 2018 Building Code
- Code List
2024 OHIO BUILDING CODE (2021 IBC)
2019 RESIDENTIAL CODE OF OHIO (2018 IRC)
2024 OHIO EXISTING BUILDING CODE (2021 IEBC)
2023 OHIO ELECTRIC CODE (2023 NFPA 70)
2021 INTERNATIONAL FIRE CODE (IFC)
- IEBC Accepted
- 1
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- How Many Plansets Required
- Other (See Submission Notes)
- Revision Required
- 0
- New Planset Required For Module Swap
- 0
Stamps
- Ee Stamp Required On SLD
- No
- Wet Stamps Required
- Digital Structural
- Structural Calculations Required
- Yes
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
On each roof plane containing photovoltaic panels, provide 36-inch pathway from lowest edge to ridge.
Not fewer than two pathways, on separate roof planes from lowest roof edge to ridge and not less than 36 inches (914 mm) wide, shall be provided on all buildings
Structural & loads
- Wind Speed
- 90
- Snow Load
- 20
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Structural Notes
AHJ requires stamped plans and structural calcs
- Minimum Ground On Roof
- #10
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Meter Adapter,PV Breaker,Load Side Taps,Line Side Taps
- Panel Schedule Required
- Partial Home Backup
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Standard
- Separate ESS Disconnect Required
- ESS Disconnect
- ESS Elevation Detail Required
- No
Plan set
- Electrical Diagram
Projects that have a SolarEdge inverter do NOT require a J-Box
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim
- Setback Front Yard
- 10
- Setback Back Yard
- 5
- Setback Side Yard
- 5