City of Temple (TX)
Codes
- NEC Code Version
- 2023
- Fire Code Version
- 2018 Building Code
- Code List
2015 INTERNATIONAL BUILDING CODE
2015 INTERNATIONAL ENERGY CONSERVATION CODE
2009 INTERNATIONAL FIRE CODE
2015 INTERNATIONAL FUEL GAS CODE
2015 INTERNATIONAL MECHANICAL CODE
2015 INTERNATIONAL PLUMBING CODE
2023 NATIONAL ELECTRICAL CODE
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- Revision Required
- 0
- Rough Inspection
- None
- New Planset Required For Module Swap
- 0
Stamps
- Ee Stamp Required On SLD
- Yes
- Wet Stamps Required
- Digital Structural,Digital Electrical
- Structural Calculations Required
- Yes
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
- Setback Notes
Standard
Structural & loads
- Wind Speed
- 115
- Wind Notes
Exposure Category B
- Snow Load
- 5
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
Electrical
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Meter Adapter,Line Side Taps,Load Side Taps,PV Breaker
- Panel Schedule Required
- Partial Home Backup
- Service Ground Requirements
USE #6 GROUND FREE AIR OR #6 GROUND IN EMT CONDUIT FROM MODULES TO JB (free air preferred)
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
- BOS Restrictions
We require an outside main service panel (MSP) or main disconnect for the house, if not already installed.
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Visible Lockable Labeled Disconnect required between battery and utility meter.
- ESS Elevation Detail Required
- No
Plan set
- Electrical Diagram
* We require an outside main service panel (MSP) or main disconnect for the house, if not already installed. * Contractor to ensure grounding complies to Temple Ordinance 10-17 a Must have a minimum of two grounding electrodes (Rods must be 8 foot driven not less than 45 degree angle and greater than 6 feet apart.) PV source and output circuits over 150v to ground installed in one and two family dwellings Shall NOT be accessible to other than qualified persons while energized. (NEC 690.7 D)
Ground mount
- Ground Mount Fencing Required
- Mesh/Scrim
- Ground Mount Notes
Setback requirements are case by case and depend on the Zoning use for the lot.
Scrim is required on ground mounts
bonding required at each coupled length