County of Mason (WA)
NEC Code Version2023
Fire Code Version2018 Building Code
Wet Stamps RequiredDigital Structural
Fire Setback Enforced1
Codes
- NEC Code Version
- 2023
- Fire Code Version
- 2018 Building Code
- Code List
2021 INTERNATIONAL BUILDING CODE
2021 INTERNATIONAL RESIDENTIAL CODE
2021 INTERNATIONAL FIRE CODE
2021 INTERNATIONAL ENERGY CONSERVATION CODE
2021 INTERNATIONAL EXISTING BUILDING CODE
2021 INTERNATIONAL FUEL GAS CODE
2021 INTERNATIONAL MECHANICAL CODE
2021 INTERNATIONAL PLUMBING CODE
2023 NATIONAL ELECTRICAL CODE
- IEBC Accepted
- 1
- ASCE Code Specification
- ASCE 7-16
SolarAPP+ & submittal
- Revision Required
- 0
- New Planset Required For Module Swap
- 0
Stamps
- Ee Stamp Required On SLD
- No
- Wet Stamps Required
- Digital Structural
- Structural Calculations Required
- Yes
- Stamp Location On Plans
- Unspecified
- Date On Stamps
- Expiration Date
Fire setbacks
- Fire Setback Enforced
- 1
Structural & loads
- Wind Speed
- 96
- Snow Load
- 5
- Reducible Snow Load Allowed
- 1
- Max Attachment Spacing
- 96
- Minimum Ground On Roof
- #10
Electrical
- AC Disconnect Required
- No
- Electrical Load Calcs Required
- Derates
- Allowed POI
- Load Side Taps,Line Side Taps,PV Breaker,Meter Adapter
- Supply Tap Neutral Ground Bond Required
- 1
- Temperature Rating
- 90
- De Rating Ampacity
- 0.91
- BOS Restrictions
Standard
Battery / ESS
- Unique Battery Placards Needed
- 0
- ESS Notes
Standard ESS requirements
- Separate ESS Disconnect Required
- No
- ESS Elevation Detail Required
- No
Plan set
- Plan Set Requirements
Electrical permit required from the State of Washington - Labor & Industries (WA). Please see page for requirements.
- Cover Page
Standard
- Site
Standard
- Roof Plan
Standard
- Attachment Detail
Standard
- Electrical Diagram
For all Line Side Connections:
- Neutral and ground bonded in fused disconnect
- #6 bare copper run from N/G bar to (E) MSP's GEC and crimped
- Schedule 80 PVC must be used in between fused disconnect and MSP - only showing 2 hots and neutral
- All other conduit can be EMT
For all Load Side Taps:
- Schedule 80 PVC must be used in between disconnect and MSP
- Label Page
Standard
Ground mount
- Ground Mount Fencing Required
- No
- Ground Mount Notes
Standard GM requirements
- Setback Front Yard
- 10
- Setback Back Yard
- 5
- Setback Side Yard
- 5