Arizona Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeAnnual
Line Taps Allowed0
Load Taps Allowed0
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
1
NEM Type
Annual
TOU Utility
0
Post Solar Billing Method
Net Metering
Solar Export Type
N/A
Net Excess Generation Notes

Net metering is accomplished using a bi-directional meter. Any customer net excess generation will be carried over to the customer's next bill at the utility's retail rate, as a kilowatt-hour credit. At the end of the calendar year (December 31), any credit balance, carried from month to month will be carried forward to the next year to the customer's account.

Rebates Offered
0
Deregulated
0
Allows Standby
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
1
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restriction Type
No Restrictions
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
Percentage
Offset Value
125
Offset Calculation Basis
Historical
Offset Calculation Period
12
Industry Standard Watts Sqft
2
Utility Specific Adjustments
  • System must be sized to meet all or part of customer's electric load and may not exceed 125% of the customer's total connected load.
System Offset Notes


Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
AC Disconnect Required
Yes
AC Disconnect Labeling
Utility AC Disconnect
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs

Must show:

  • Major equipment
  • Electric service entrance
  • Utility meter
  • Inverter
  • Interface equipment
  • Disconnect switch
  • Major cross streets and project location
SLD Reqs
  • must show connections, bus size, circuit breakers, fuses etc. between main electrical components such as meter(s), main panel, main disconnect switch/breaker, PV breaker, ac utility disconnect switch, PV inverter(s), sub-panel, loads, etc.
  • One-Line Diagram and Three-Line Diagram required
Install Reqs
  • Install switch gear and protective equipment that will prevent back feed into the Safford system in order to maintain system safety.
Electrical Stamp Required
0
Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
0
ESID Num Req SLD 3LD
0
Electrical Diagram Notes


Website
link
Phone
(928) 432-4221