Solar Sanity Checksolar, decoded Independent. Nothing you type leaves your browser.

Town of Wickenburg

Arizona Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeMonthly
Supply Side Taps Allowed0
Line Taps Allowed0
Load Taps Allowed0

Net metering & export

Net Metering Allowed
1
NEM Type
Monthly
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

The customer will recieve a monthly bill for the base charge and any usage over that of generation. In the event no usage is required there will not be a kwh charge. The Town of Wickenburg does NOT pay the customer for excess power returned to the grid.

Rebates Offered
0
Deregulated
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Supply Side Taps Allowed
0
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Meter Spot Process

TDR Process: Notify the Town at least 48 hours.

Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs

Follows APS requirements

SLD Reqs

Follows APS requirements

Install Reqs

All transfer switches utilized to serve an electrical load from either the Town of Wickenburg's Electric Grid or an alternate power generation or storage source

shall prevent both sources from being paralleled or simultaneously interconnected. Transfer switches for this application shall be "break-before-make" transfer scheme using open transition style transfer switches.

Equipment Approvals
California Energy Commission
Website
link
Phone
(928) 684-5451

Other details

Restrict Inspection
0
Address ID
677220
Express Planset Eligible
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Town of Wickenburg before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.