AEC - Anza Electric Cooperative

California Utility Interconnection & net metering rules
Net Metering Allowed0
Supply Side Taps Allowed0
Line Taps Allowed0
Load Taps Allowed0

Net metering & export

Net Metering Allowed
0
TOU Utility
0
Post Solar Billing Method
Export Rate
Solar Export Type
Avoided Cost
Solar Export Rate Approx
0.0819
Solar Export Value Notes
This cost consists of the average cost of kWh purchased less AB32 charges less the cost of transmission.
Net Excess Generation Notes

The excess kWh generated by the DG facility will be purchased at avoided cost.

Rebates Offered
0
Deregulated
0
Allows Standby
1

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Supply Side Taps Allowed
0
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
0

System size & offset

System Size Restrictions
5
System Size Restriction Type
DC kW
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

Generating facility nameplate rating is limited as follows:

• Rate Schedule DG-1 and DG-2: Maximum of 5 KW DC or 100% offset (whichever is less)

• Rate Schedule DG-10, DG-14 and DG-20: Maximum of 10 KW DC or 100% offset (whichever is less)

Offset Calc Tool
PV Watts

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Meter Spot Process

The utility will disconnect the service in the morning and reconnect after the county has inspected the new panel. (no cost as long as we can schedule during normal working hours).


Contact: staff (Meter & Energy Services Technician)


58470 Highway 371 (P.O. Box 391909) Anza, CA 92539


Ext: 212 or Fax

Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs
  • All equipment displayed
  • Include spec sheets for junction boxes
SLD Reqs
  • Utility Meter must be displayed

spec sheets required for battery projects:

lug kit

back up load panel

PV system shutdown switch

Install Reqs

Everything installed must match plans

Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
0
ESID Num Req SLD 3LD
0
Rate Schedule Link
link
Website
link
Phone
951-763-4333

Other details

Restrict Inspection
0
Revision Required
0
Mod Swap Requires Planset
1
Address ID
108033
Express Planset Eligible
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with AEC - Anza Electric Cooperative before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.