City of Ukiah

California Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Supply Side Taps AllowedYes
Line Taps AllowedYes
Load Taps AllowedYes

Net metering & export

Rebates Offered
No

Interconnection & taps

Approval Req To Install
Yes
Supply Side Taps Allowed
Yes
Line Taps Allowed
Yes
Load Taps Allowed
Yes
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
Percentage
Offset Value
100
Offset Calculation Basis
Historical
Offset Calculation Period
12
Industry Standard Watts Sqft
2
Utility Specific Adjustments

To ensure grid safety and reliability, sizing of the generation (in kW) will be limited to two times customer load up to 10 kW AC maximum.

Generation over 10 kW shall be subject to special review to ensure grid safety. Cost of studies and upgrades associated with generation over 10 kW will be established during the permitting process and paid prior to connection. 

System Offset Notes

To ensure grid safety and reliability, sizing of the generation (in kW) will be limited to two times customer load up to 10 kW AC maximum.

Generation over 10 kW shall be subject to special review to ensure grid safety. Cost of studies and upgrades associated with generation over 10 kW will be established during the permitting process and paid prior to connection. 

Offset Calc Tool
CSI

Metering & disconnect

Production Meter Required
No
Allowed Meter Adapter
None

Plans & docs

SLD Reqs

**City of Ukiah Utility jobs:**


* A lockable FUSED disconnect device shall be installed between the alternate engery source and the Service Entrance Panel. Fuse Rating to match conductor ampacity. The fused disconnect must be within 10' of the Service Entrance Panel and must be accessible to the City at all times (include note on Site plan similar to APS utility)

*

*

* System size cannot exceed annual usage - for system sizes greater than 5KW, must show justification (for construction review - similar to NVE requirement)

* PV Modules must be included on the approved list www.gosolarcalifornia.org/equipment/pv_modules.php (http://www.gosolarcalifornia.org/equipment/inverters.php)

* Inverters must be included on the approved list www.gosolarcalifornia.org/equipment/inverters.php (http://www.gosolarcalifornia.org/equipment/inverters.php)

* PVWatts must be submitted for projects that exceed "minimal shading" (not defined by city)

* City/utility must have 24 hours unrestricted access to the solar equipment (similar to APS)


LINE SIDE TAPS ARE THE ONLY WAY WE CAN CONNECT OUR SOLAR TO THE GRID AHJ WILL KICK BACK PROJECT IF WE USE PV BREAKER.

Electric Service Reqs

1. CSI Annual kWh to not exceed customer's annual usage.

2. For new construction or if electric consumption history does not reflect expected expanded consumption, includes an electrical load estimate for PV system larger than 5kW ac. Suggested methods of substantiating a load estimate include an electric load calculation with corresponding equipment schedules. building simulation program reports, or detailed engineering calculations.

Install Reqs

All projects over 10kW require a feeder study, which must be completed before install approval has been issued.

Equipment Approvals
California Energy Commission
Electrical Diagram Notes

City of Ukiah - Production Meter not required for residential solar installations only commercial.

Rate Schedule Link
link
Website
link
Phone
707-463-6203
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with City of Ukiah before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.