Pacific Power (CA)
Net Metering Allowed1
Supply Side Taps Allowed0
Line Taps Allowed0
Load Taps Allowed0
Net metering & export
- Net Metering Allowed
- 1
- Post Solar Billing Method
- Net Metering
- Rebates Offered
- 0
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Supply Side Taps Allowed
- 0
- Line Taps Allowed
- 0
- Load Taps Allowed
- 0
- Automatic Transformer Upgrade Size
- 0
- Meter Aggregation Allowed
- 1
System size & offset
- System Size Restrictions
- 0
- System Size Restriction Type
- No Restrictions
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Type
- No Restrictions
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
Metering & disconnect
- Production Meter Required
- No
- Production Meter Position
- N/A
- Production Meter Labeling
- N/A
- Allowed Meter Adapter
- ConnectDER,Tesla Backup Switch
Plans & docs
- Site Plan Reqs
Show distance from AC Disconnect to Utility Meter (UM).
- CA: within 3 feet from the UM
- OR: within 10 feet from the UM
- WA: within 3 feet from the UM
- SLD Reqs
A one-line diagram showing:
- The location of Utility Meter (UM)
- The location of the disconnect switch
FOR BATTERIES: - ESS DISCONNECT REQUIRED
- Install Reqs
After installation, schedule an appointment to have the Net Meter set by calling .
Submit a photo of the installed placards with Request for Inspection.
- Placards
See "Key Components Solar Generation System" and examples in Files section of this page.
- Website
- link
- Phone
- 1-800-625-6078; 203-813-7496
Other details
- Restrict Inspection
- 0
- Address ID
- 108067
- Express Planset Eligible
- Yes