Net Metering AllowedYes
Line Taps AllowedNo
Load Taps AllowedNo

Net metering & export

Net Metering Allowed
Yes
Post Solar Billing Method
Net Metering
Rebates Offered
No

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

The RGS must have a GPR that does not exceed ninety percent (90%) of the Customer's utility distribution service rating at the Customer's location. If the GPR does exceed that ninety percent (90%) limit, the Customer shall be responsible to pay the cost of upgrades for that distribution service to accommodate the GPR capacity and to ensure the ninety percent (90%) threshold is not breached.

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Allowed Meter Adapter
None

Plans & docs

Rate Schedule Link
link
Website
link
Phone
(386) 362-2226