Net Metering AllowedYes
NEM TypeMonthly
Line Taps AllowedNo
Load Taps AllowedNo
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
Yes
NEM Type
Monthly
TOU Utility
No
Post Solar Billing Method
Net Metering
Solar Export Type
Avoided Cost
Solar Export Rate Approx
0.03
Net Excess Generation Notes

The rate used to determine the dollar amount paid for net energy purchased by the Cooperative shall be based upon the Cooperative’s avoided average annual cost of purchased power. The purchase rate as of the effective date of this Rider shown below is: All kWh $0.031 per kWh

However, the Cooperative will only be required to purchase such energy from Customer Generators on a first-come, first-served basis until the cumulative generating capacity of all the Customer Generators’ renewable energy resources equals 0.2 percent of the Cooperative’s annual peak demand in the previous year.

Rebates Offered
No
Deregulated
Yes

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
No

System size & offset

System Size Restrictions
10
System Size Restriction Type
AC kW
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes


Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Allowed Meter Adapter
None

Plans & docs

SLD Reqs

"a detailed one-line diagram of the proposed facility, all applicable elementary diagrams, major equipment, (generators, transformers, inverters, circuit breakers, protective relays, etc.) specifications, test reports, etc., and any other applicable drawings or documents

necessary for the proper design of the interconnection. Also describe the project’s planned operating mode (e.g., combined heat and power, peak shaving, etc.)."

Electric Service Reqs


Electrical Stamp Required
Yes
Meter Num Req SLD 3LD
No
ESID Num Req SLD 3LD
No
Website
link
Phone
(706) 845-2000

Other details

Revision Required
No
Mod Swap Requires Planset
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Diverse Power before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.