OREMC - Okefenoke Rural Electric Membership Corporation
Supply Side Taps Allowed0
Line Taps Allowed0
Load Taps Allowed0
Net metering & export
- Rebates Offered
- 0
- Allows Standby
- 0
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Supply Side Taps Allowed
- 0
- Line Taps Allowed
- 0
- Load Taps Allowed
- 0
- Automatic Transformer Upgrade Size
- 0
- Meter Aggregation Allowed
- 0
System size & offset
- System Size Restrictions
- 250
- System Size Restriction Type
- AC kW
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Type
- No Restrictions
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- System Offset Notes
Has a capacity rating of no greater than 250 kW (AC).
Metering & disconnect
- Production Meter Required
- No
- Production Meter Position
- N/A
- Production Meter Labeling
- N/A
- Allowed Meter Adapter
- None
Plans & docs
- Site Plan Reqs
AC Disconnect must be within 6ft of Meter
- Equipment Approvals
- California Energy Commission
- Website
- link
- Phone
- (800) 262-5131
Other details
- Restrict Inspection
- 0
- Address ID
- 117996
- Express Planset Eligible
- Yes