City of Geneva Utilities

Illinois Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeAnnual
Line Taps Allowed0
Load Taps Allowed0

Net metering & export

Net Metering Allowed
1
NEM Type
Annual
TOU Utility
0
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

Customers will not be paid for any energy “pushed” onto the grid. Credits for unused energy are accumulated starting May 1 and continue to be accrued throughout the year. On April 30, any unused energy credits are zero’d out and the accruals start fresh on May 1. These dates coincide with the beginning and end of the City's fiscal year.

Rebates Offered
0
Deregulated
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
0

System size & offset

System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

No size restrictions, other than constraints such as service size. Most systems run between 6 to 8 kW based on roof sizes here.

Offset Calc Tool
N/A

Metering & disconnect

Production Meter Required
Yes
Production Meter Position
Inv-PM-Disco-POI
Production Meter Labeling
Production Meter
Meter Spot Process

Temporary Disconnect Reconnect Process (TDR) We ask for 48 hours’ notice in advance for a disconnect and reconnects. Any reconnect done after 3:00pm would incur overtime costs and would be billed to the contractor.

TDR - Who to Contact staff

TDR - Applications/Documents Req N/A

TDR - ETA of notice required for request 48 hours

TDR - Who can schedule? Does not matter

TDR - ETA of Utility Scheduling TDR N/A

Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs

Standard

SLD Reqs

Instructions for One-Line Diagram - Attached

Install Reqs

Any UL approved 100/200 amp single phase meter socket (for residential installations). City of Geneva will provide the production meter. Often, for commissioning, the installer will use their own meter. We will return the installer’s meter after the City’s meter is set.

Website
link
Phone
(630) 232-1503

Other details

Restrict Inspection
0
Address ID
271527
Express Planset Eligible
No
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with City of Geneva Utilities before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.