TMLP - Templeton Municipal Light & Water Plant
Net metering & export
- Net Metering Allowed
- 1
- NEM Type
- Monthly
- TOU Utility
- 0
- Post Solar Billing Method
- Net Metering
- Net Excess Generation Notes
During any regular billing interval, if the electric customer feeds back more KWH to the TMLWP system than it uses, then said customer shall be billed the minimum charge applicable to the electric customer’s class of service. Further, the electric customer’s account shall be credited for the excess KWH generated and fed back to the TMLWP system. Any such excess KWH shall carry forward from one billing interval to the next until said excess has been utilized.$0.0286 per Net KWH Received. ** One cent ($0.0100) discount per KWH for lighting customers if paid within ten (10) days of date of invoice **
- Rebates Offered
- 0
- Deregulated
- 1
- Allows Standby
- 0
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Line Taps Allowed
- 0
- Load Taps Allowed
- 0
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Restrictions
- 10
- System Size Restriction Type
- AC kW
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Type
- No Restrictions
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- System Offset Notes
Up to 10kW for Net Metering
- Offset Calc Tool
- N/A
Metering & disconnect
- Production Meter Required
- Yes
- Production Meter Position
- Inv-Disco-PM-POI
- Production Meter Labeling
- Production Meter
- AC Disconnect Required
- Yes
- AC Disconnect Labeling
- Utility Disconnect Switch
- Allowed Meter Adapter
- None
Plans & docs
- SLD Reqs
The one line should show the entire system including # of panels, inverters, circuits, main panel, production meter, disconnects and wiring. A production meter is required (to be provided by TMLP). A disconnect accessible to TMLP must be installed near the utility meter.
** Massachusetts Registered Professional Engineer (PE) stamp required for projects larger than 10kW AC **
- Electric Service Reqs
AC Disconnect Required
refer to drawing B1, “Interconnection Requirements for single phase inverter-based generator less than 10 kW” and note that a lockable disconnect switch is required on the outside of the home near the utility meter accessible to TMLP
- Install Reqs
Production Meter Required
- Electrical Stamp Required
- 1
- Equipment Approvals
- California Energy Commission
- Meter Num Req SLD 3LD
- 0
- ESID Num Req SLD 3LD
- 0
- Website
- link
- Phone
- (978) 939-5323
Other details
- Restrict Inspection
- 0
- Address ID
- 128645
- Express Planset Eligible
- No