BENCO Electric Coop (MN)

Minnesota Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Net Metering AllowedYes
NEM TypeAnnual
Line Taps AllowedNo
Load Taps AllowedNo
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
Yes
NEM Type
Annual
TOU Utility
No
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

Kilowatt-hours produced by the QF in excess of the monthly usage shall be supplied as an energy credit on the member’s energy bill, carried forward and applied to subsequent energy bills, with an annual true-up on December 31. Excess energy credits existing as of December 31 shall default back to the Cooperative with no compensation to the QF.

Rebates Offered
Yes
Deregulated
No
Allows Standby
No

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
Yes

System size & offset

System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

40 kW or less: System doesn't have any offset requirement

System over 40 kW: 120% offset

Offset Calc Tool
Historical Usage

Metering & disconnect

Production Meter Required
Yes
Production Meter Position
Inv-Disco-PM-POI
Production Meter Labeling
Production Meter
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect

Plans & docs

Site Plan Reqs

SLD Reqs

Electric Service Reqs


Install Reqs


Placards


Electrical Stamp Required
No
Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
No
ESID Num Req SLD 3LD
No
Rate Schedule Link
link
Website
link
Phone
(507) 387-7963

Other details

Revision Required
Yes
Mod Swap Requires Planset
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with BENCO Electric Coop (MN) before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.