McLeod Coop Power

Minnesota Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeMonthly
Line Taps Allowed0
Load Taps Allowed0
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
1
NEM Type
Monthly
TOU Utility
0
Post Solar Billing Method
Net Metering
Solar Export Type
Avoided Cost
Net Excess Generation Notes

When the energy generated by the qualifying facility exceeds that supplied by the Cooperative during a billing period, the Cooperative shall apply the excess kilowatt hours as a credit to the next billing period kilowatt hour usage. Excess kilowatt hours that are not offset in the next billing period shall continue to be rolled over to the next consecutive billing period. Any excess kilowatt hours rolled over that are remaining at the end of each calendar year shall cancel with no additional compensation. 

Rebates Offered
0
Deregulated
0
Allows Standby
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
1

System size & offset

System Size Restrictions
40
System Size Restriction Type
AC kW
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
Inverter Oversize Restrictions
0
System Offset Notes

System can be sized up to 40 kW AC w/ no offset restriction.

Systems over 40 kW AC will have an 120% offset requirement

Offset Calc Tool
Historical Usage

Metering & disconnect

Production Meter Required
Yes
Production Meter Position
Inv-Disco-PM-POI
Production Meter Labeling
Production Meter
AC Disconnect Required
Yes
AC Disconnect Labeling
Utility Disconnect Switch
Allowed Meter Adapter
None,None

Plans & docs

SLD Reqs


Install Reqs

All self-contained meter sockets must be a bypass type socket with a manually operated lever bypass

Placards
  1. PM needs to read as Production Meter
Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
1
ESID Num Req SLD 3LD
0
Electrical Diagram Notes


Rate Schedule Link
link
Website
link
Phone
(320) 864-3148

Other details

Restrict Inspection
0
Revision Required
1
Mod Swap Requires Planset
1
Address ID
9949628
Express Planset Eligible
No
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with McLeod Coop Power before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.