Citizens Electric Corporation

Missouri Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeMonthly
Line Taps Allowed0
Load Taps Allowed0
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
1
NEM Type
Monthly
TOU Utility
0
Post Solar Billing Method
Net Metering
Solar Export Type
N/A
Net Excess Generation Notes

The value of that amount of electric energy delivered by Member-Generator to the Corporation’s system in excess of the amount of electric energy consumed by the Member-Generator shall be determined by multiplying the number of excess kWh delivered by Member-Generator to the Corporation by the average monthly kWh charge from Wabash Valley Power Association, Inc. (ā€œWVPAā€) during the billing period. The Member-Generator shall receive credits equal to the value of the electric energy delivered to the Corporation. Credits will be applied to the next billing period following issuance of the credits. The credits shall expire without any compensation at the earlier of either twelve months after their issuance or when the Member-Generator disconnects service or terminates the net metering relationship with the Corporation.

Rebates Offered
0
Deregulated
0
Allows Standby
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Tap Criteria


Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
0

System size & offset

System Size Restrictions
100
System Size Restriction Type
AC kW
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
Inverter Oversize Restrictions
0
System Offset Notes

The utility does not have any specific offset limit, however the systems should be sized reasonably to accommodate the homeowner's usage.

Metering & disconnect

Production Meter Required
No
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect

Plans & docs

Site Plan Reqs

Standard site plan requirements

SLD Reqs


Electrical Stamp Required
0
Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
0
ESID Num Req SLD 3LD
0
Rate Schedule Link
link
Website
link
Phone
(877) 876-3511

Other details

Restrict Inspection
0
Revision Required
1
Mod Swap Requires Planset
1
Address ID
3877594
Express Planset Eligible
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Citizens Electric Corporation before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.