Citizens Electric Corporation

Missouri Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Net Metering AllowedYes
NEM TypeMonthly
Line Taps AllowedNo
Load Taps AllowedNo
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
Yes
NEM Type
Monthly
TOU Utility
No
Post Solar Billing Method
Net Metering
Solar Export Type
N/A
Net Excess Generation Notes

The value of that amount of electric energy delivered by Member-Generator to the Corporation’s system in excess of the amount of electric energy consumed by the Member-Generator shall be determined by multiplying the number of excess kWh delivered by Member-Generator to the Corporation by the average monthly kWh charge from Wabash Valley Power Association, Inc. (“WVPA”) during the billing period. The Member-Generator shall receive credits equal to the value of the electric energy delivered to the Corporation. Credits will be applied to the next billing period following issuance of the credits. The credits shall expire without any compensation at the earlier of either twelve months after their issuance or when the Member-Generator disconnects service or terminates the net metering relationship with the Corporation.

Rebates Offered
No
Deregulated
No
Allows Standby
No

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
No
Load Taps Allowed
No
Tap Criteria


Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
No

System size & offset

System Size Restrictions
100
System Size Restriction Type
AC kW
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
Inverter Oversize Restrictions
No
System Offset Notes

The utility does not have any specific offset limit, however the systems should be sized reasonably to accommodate the homeowner's usage.

Metering & disconnect

Production Meter Required
No
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect

Plans & docs

Site Plan Reqs

Standard site plan requirements

SLD Reqs


Electrical Stamp Required
No
Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
No
ESID Num Req SLD 3LD
No
Rate Schedule Link
link
Website
link
Phone
(877) 876-3511

Other details

Revision Required
Yes
Mod Swap Requires Planset
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Citizens Electric Corporation before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.