Central Electric (NC)
Net metering & export
- Net Metering Allowed
- 1
- NEM Type
- Monthly
- Post Solar Billing Method
- Net Metering
- Solar Export Type
- Avoided Cost
- Solar Export Rate Approx
- 0.0525
- Net Excess Generation Notes
"There are two(2) Riders but their rates/requirements are similar. The SMALL CONSUMER-OWNED GENERATOR RIDER is for systems where The nameplate rating of the Renewable Generation is the lesser of the consumer’s historical maximum 15- minute integrated demand or 10 kW. The PURCHASED POWER RIDER is for systems less than 500kW.
Consumers generating power from a renewable resource, as defined in this Rider, shall be billed for all energy and kW demand, if applicable, that is delivered by the Cooperative under the rate schedule the consumer receives service, plus any applicable riders, during the billing month.
The consumer will receive credits for all excess energy delivered to the Cooperative’s system during the billing month at the rate of 5.25 cents ($0.0525) per kWh and is subject to change based upon the Cooperative’s estimated avoided cost of wholesale purchased power.
The consumer’s service may be metered with: (a) a single, bi-directional meter, which records independently the flow of electricity in each direction through the meter; or (b) at the Cooperative’s option, two meters, equipped to prevent reverse registration, one which will measure the energy delivered by the Cooperative to the consumer, and the other which will measure the energy delivered by the consumer to the Cooperative. The Cooperative shall have the right to install special metering and load research devices on the consumer’s equipment and the right to use the consumer’s telephone line for communication with the Cooperative’s and the consumer’s equipment. "
- Rebates Offered
- 0
- Deregulated
- 0
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Line Taps Allowed
- 0
- Load Taps Allowed
- 0
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Restrictions
- 10
- System Size Restriction Type
- AC kW
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Type
- No Restrictions
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- System Offset Notes
10kW AC is max
- Offset Calc Tool
- PV Watts
Metering & disconnect
- Production Meter Required
- No
- AC Disconnect Required
- Yes
- Meter Spot Process
Temporary Disconnect Reconnect Process (TDR) No Fees and if power must be cut-off to do the work, call our office a couple days in advance. Give a time when to have it off and you will need to call our office back when power is to be restored.
TDR - Who to
TDR - Applications/Documents Req N/A
TDR - ETA of notice required for request N/A
TDR - Who can schedule? Does not matter
TDR - ETA of Utility Scheduling TDR N/A
- Allowed Meter Adapter
- None
Plans & docs
- Site Plan Reqs
Member shall install a manual load-break disconnect switch with a clear visible indication of switch position between Company's electric system and Member's Generator. It is preferred the Isolation Device be within five feet (5’) of the meter base
- SLD Reqs
No Production Meter Required
- Placards
Member will install a permanent warning label in a conspicuous place in close proximity to the electric meter or on the meter base to notify Company personnel that there is a generator installed on the load side of the meter. The warning label shall not be placed in a location that would interfere with the ability of Company personnel to read the electric meter. Member shall also place a warning label on the Isolation Device. The warning labels must be in place before the Generator can be interconnected with Company's system.
- Website
- link
- Phone
- (800) 446-7752
Other details
- Restrict Inspection
- 0
- Revision Required
- 1
- Mod Swap Requires Planset
- 1
- Address ID
- 161245
- Express Planset Eligible
- Yes