City of New Burn

North Carolina Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Net Metering AllowedYes
Line Taps AllowedNo
Load Taps AllowedNo

Net metering & export

Net Metering Allowed
Yes
Post Solar Billing Method
Feed-in-Tariff
Solar Export Type
Avoided Cost
Solar Export Rate Approx
0.0487
Solar Export Value Notes
The customers service shall be metered with two meters - one to measure all energy provided by the City and used by the customer, and all other to measure the amount of energy generated by th
Rebates Offered
No
Deregulated
Yes
Allows Standby
No

Interconnection & taps

Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0

System size & offset

System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with City of New Burn before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.