Net metering & export
- Net Metering Allowed
- 1
- Post Solar Billing Method
- Net Metering
- Rebates Offered
- 1
- Allows Standby
- 1
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Line Taps Allowed
- 1
- Load Taps Allowed
- 1
- Automatic Transformer Upgrade Size
- 0
System size & offset
- System Size Restrictions
- 0
- System Size Restriction Type
- No Restrictions
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Type
- No Restrictions
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- System Offset Notes
We do not limit the size system you wish to install and will perform our analysis based on the system size you propose. There may be system modifications required as the system size increases and those are identified during the analysis phase. An example of this would be upgrading the size of the distribution transformer that serves the Customer.
- Offset Calc Tool
- N/A
Metering & disconnect
- Production Meter Required
- No
- Production Meter Position
- N/A
- Production Meter Labeling
- N/A
- Allowed Meter Adapter
- None
Plans & docs
- Site Plan Reqs
Site plan Including location of:
Interconnecting transformer
Interconnection device
Point of Common Coupling
Point of Interconnection
Line Extension
- SLD Reqs
- The system showing all switching and protective devices and the tie point to the utility system.
- The one-line shall include all Current transformers and Voltage Transformers with all ratios.
- Electric Service Reqs
An ESS Questionnaire must be filled out by design for all battery projects. A blank copy of this form is uploaded to the Files section below titled "Unitil ESS Questionnaire." Example project Forever Portal Example completed form OneDrive
- Placards
Site placard to label utility meter as "net meter"
- Website
- link
- Phone
- (630) 773-6480
Other details
- Restrict Inspection
- 0
- Address ID
- 134359
- Express Planset Eligible
- Yes