Otero County Electric Cooperative

New Mexico Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Net Metering AllowedYes
NEM TypeMonthly
Supply Side Taps AllowedYes
Line Taps AllowedYes
Load Taps AllowedYes
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
Yes
NEM Type
Monthly
TOU Utility
No
Post Solar Billing Method
Net Metering
Solar Export Type
Avoided Cost
Solar Export Rate Approx
0.02
Net Excess Generation Notes

"The qualifying facility shall be billed for the net energy delivered from the utility in accordance with the

tariffs that are applicable to the qualifying facility. At the end of the billing period the utility shall net all charges owed to the utility by the qualifying facility. If a net amount is owed to the qualifying facility for the billing period, and is less than $50, the payment amount may be carried over to the following billing period. If a net amount is owed to the qualifying facility and is $50 or more, the utility shall make payment to the qualifying facility prior to the end of the next billing period. "

Rebates Offered
No
Deregulated
No

Interconnection & taps

Approval Req To Install
Yes
Supply Side Taps Allowed
Yes
Line Taps Allowed
Yes
Load Taps Allowed
Yes
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
Percentage
Offset Value
120
Offset Calculation Basis
Historical
Offset Calculation Period
12
Industry Standard Watts Sqft
2
System Offset Notes

You cannot generate more than 120% of a year’s usage. It also depends if a certain feeder is oversaturated with PV, then we look at each system individually to determine if there will back feed on our transmission system.

Offset Calc Tool
Historical Usage

Metering & disconnect

Production Meter Required
Yes
Production Meter Position
Inv-Disco-PM-POI
Production Meter Labeling
Production Meter
AC Disconnect Required
Yes
Allowed Meter Adapter
None

Plans & docs

SLD Reqs

Meter Orientation = Over/Under


REC METER REQUIRED: The wiring from the solar side should be on the top lugs of the meter. The bottom lugs should go to the utility side. 

Electric Service Reqs

Must meet NMPRC Ruling 568 and NMPRC Ruling 570

Install Reqs

We would encourage all interconnections to include the installation of a meter base for a Renewable Energy Certificate (REC) meter. In addition to the benefits of the utility meter registering the net of forward and reverse consumption, the REC meter, installed on the output (AC side) of the inverter, would register everything your unit would generate. Every 1,000 kilowatt-hours generated would create one REC, which for systems 25 kW and smaller, OCEC would then purchase at a defined rate of $1.00 per REC.  

Rate Schedule Link
link
Website
link
Phone
(800) 548-4660
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Otero County Electric Cooperative before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.