Freeport Electric

New York Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Net Metering AllowedYes
NEM TypeAnnual
Line Taps AllowedNo
Load Taps AllowedNo
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
Yes
NEM Type
Annual
TOU Utility
No
Post Solar Billing Method
Net Metering
Solar Export Type
Fixed kWh
Net Excess Generation Notes

a. If a Customer produces more energy than consumed during an individual billing cycle a kWh credit will be carried forward until consumed or the end of the calendar year as described below.

b. If a Customer produces more energy than consumed during any calendar year;

1. Following the first billing cycle that ends on or after the last day of each calendar year the Village will issue a credit to the customer.

2. The credit will be calculated by multiplying the kWh credit balance times the average of the Average Cost of Fuel from the Village’s monthly Statements of Fuel Adjustment Cost filed during the past 12 months, adjusted by the Factor of Adjustment.

3. The kWh credit balance shall be reset to zero once payment is made.

Rebates Offered
No
Deregulated
Yes
Allows Standby
Yes

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
Yes

System size & offset

System Size Restrictions
10
System Size Restriction Type
AC kW
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
Combination
Offset Value
100
Offset Calculation Basis
Historical
Offset Calculation Period
12
Industry Standard Watts Sqft
2
System Offset Notes
  • System design output shall not exceed 100% of the prior 12 months metered energy consumption. 
Offset Calc Tool
Historical Usage

Metering & disconnect

Production Meter Required
No
AC Disconnect Required
Yes
AC Disconnect Labeling
Utility Disconnect Switch
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs
  • The disconnect switch shall be installed, owned, and maintained by the customer-generator, and located between the generating equipment and its interconnection point with the utility system
  • The disconnect must be accessible to the utility 24/7
  • Utility account & meter number must be listed
  • Must include a snip from Google Earth, Bing Maps, or a similar satellite site identifying the prosed interconnection point
SLD Reqs
  • Utility account & meter number must be listed
  • Number, individual ratings, connection configurations, and type of all major electrical components such as generating units, step-up transformers, auxiliary transformers, grounding transformers, neutral reactors, and switches/disconnects of the proposed interconnection, including the required protection devices (instrument transformer configuration and polarity if applicable) and circuit breakers.
  •  Proposed inverter protection settings (and relay equipment settings if applicable).
  • Proposed generator step-up transformer MVA ratings, impedances, tap settings, neutral connections, winding configurations, and voltage ratings.
  • Control system designs, phase sequencing, differential relay settings, ground connections, and metering transformer connections.
  • Batteries require their own disconnect
Placards
  • The disconnect switch shall be clearly marked, "Generator Disconnect Switch," with permanent 3/8 inch or larger letters.
Equipment Approvals
Other
Equipment Approval Other
It is recommended that equipment be selected from the Department of Public Service “Certified Interconnection Equipment list” maintained on the Commission’s website
Meter Num Req SLD 3LD
Yes
ESID Num Req SLD 3LD
No
Website
link
Phone
(516) 377-2262

Other details

Revision Required
No
Mod Swap Requires Planset
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Freeport Electric before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.