OK - Verdigris Valley Electric Coop

Oklahoma Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Net Metering AllowedYes
NEM TypeMonthly
Line Taps AllowedNo
Load Taps AllowedNo
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
Yes
NEM Type
Monthly
TOU Utility
No
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

When the energy supplied by the member exceeds the energy supplied by the Cooperative during a billing period, the monthly charge and/or minimum bill of the retail rate schedule shall be billed by the Cooperative in addition to the monthly metering charge, and the excess energy shall be purchased at the Cooperative’s Power Supplier’s avoided cost as determined by the Cooperative’s Power Supplier as a credit on the member's next bill.


Avoided cost = $0.02 - $0.04 / kWh (changes monthly and/or as needed)

Rebates Offered
No
Deregulated
No
Allows Standby
No

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
125
System Size Restriction Type
Percent
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
Inverter Oversize Restrictions
No
System Offset Notes

For Net Metering System:

  • 25 kW AC or 125% of the customer's historical usage (whichever is less)

System can be sized over 25 kW AC but will not be eligible for Net Metering = not recommended

Offset Calc Tool
Historical Usage

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
AC Disconnect Required
Yes
AC Disconnect Labeling
Utility Disconnect Switch

Plans & docs

Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
Yes
ESID Num Req SLD 3LD
Yes
Rate Schedule Link
link
Website
link
Phone
(918) 371-2584

Other details

Revision Required
Yes
Mod Swap Requires Planset
Yes