City of Ashland (OR)

Oregon Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Net Metering AllowedYes
NEM TypeAnnual
Line Taps AllowedNo
Load Taps AllowedNo
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
Yes
NEM Type
Annual
TOU Utility
No
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

Net electricity generated will be carried forward each billing cycle where a surplus exists. Accumulated net electricity will be converted from a kilowatt to dollar amount credit each based on the Municipal Utility’s wholesale rate on the next available billing cycle after March 31 of each year.

Rebates Offered
Yes
Deregulated
Yes

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
Yes

System size & offset

System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
Offset Calc Tool
Historical Usage

Metering & disconnect

Production Meter Required
No
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs

In order for the customer to be eligible for the rebate, the customer must have 2kW of qualifying panels with a 75% minimum TSRF (total solar resource fractions)

  • For single inverter systems, identify the location on the plans with the lowest TSRF.
  • For micro inverter systems, identify each panel location on the plan and provide corresponding TSRFs
  • For micro inverters serving multiple panels, identify each panel location on the plans and provide corresponding PSRF's, and identify each group of panels served by each micro inverter.
SLD Reqs

Standard

Electric Service Reqs

AC Disconnect Required

Electrical Stamp Required
No
Equipment Approvals
California Energy Commission
Meter Num Req SLD 3LD
No
ESID Num Req SLD 3LD
No
Website
link

Other details

Revision Required
Yes
Mod Swap Requires Planset
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with City of Ashland (OR) before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.