Net Metering AllowedYes
NEM TypeAnnual
Line Taps AllowedNo
Load Taps AllowedNo
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
Yes
NEM Type
Annual
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

If the amount of the electricity fed back to MW&L during the billing period by Customer-generator exceeds the amount of electricity supplied by MW&L to Customer-generator, then MW&L will bill Customer generator the minimum monthly charge(s) paid by other customers of MW&L in the same rate class as Customer-generator and carry forward to the next billing period a credit for the excess kilowatt-hour generation fed back to MW&L. For the billing cycle ending at end of fiscal year, June 30, any remaining unused kilowatt-hour credit accumulated during the previous year shall be credited to the Customer-generators at MW&L’s then applicable avoided energy cost rates, as determined in the sole discretion of MW&L.

Rebates Offered
No
Deregulated
No

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
Yes

System size & offset

System Size Restriction Type
N/A
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

Level 1 - up to 25 kW (systems below 25 kW may trigger engineering review/study for transformer upgrade)

Level 2 - 25.01 - 200 kW (or if project requires transformer upgrade)

Offset Calc Tool
N/A

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
AC Disconnect Required
Yes
AC Disconnect Labeling
Visible Lockable Labeled Disconnect
Allowed Meter Adapter
None

Plans & docs

Equipment Approvals
California Energy Commission
ESID Num Req SLD 3LD
No
Website
link
Phone
(503) 472-6158

Other details

Revision Required
Yes