Solar Sanity Checksolar, decoded Independent. Nothing you type leaves your browser.

Salem Electric (OR)

Oregon Utility Interconnection & net metering rules
Net Metering Allowed1
NEM TypeAnnual
Line Taps Allowed0
Load Taps Allowed0

Net metering & export

Net Metering Allowed
1
NEM Type
Annual
Post Solar Billing Method
Net Metering
Net Excess Generation Notes

"Effective October 1, 2019, each monthly billing period Salem Electric will charge a member-generator the monthly facilities charge and all applicable charges for the net electricity that Salem Electric delivered. If in a monthly billing period a member-generator has supplied to Salem Electric more electricity than Salem Electric has delivered to the member-generator, Salem Electric will apply the excess kWhs as a cumulative credit to the member-generator’s monthly bill. Salem Electric will apply such credit at the avoided cost rate for each component on the bill that uses kWhs as the billing determinant.


Systems installed prior to October 1, 2019, will be paid on an annual true-up through April 1, 2040. For the billing cycle ending in March of each year, or at any other time the member discontinues service at the net-metered account, if any unused credits accumulated during the previous 12 months remain, Salem Electric will pay the member-generator an amount equal to the unused credited kWhs times the average wholesale price of power purchased by Salem Electric. Modifications of existing net-metered PV systems that require a new net-metering agreement immediately revokes the application of annual true-up credit, changing the credit determination to a monthly true up credit. The annual true up is non-transferrable. After April 2040, all net-metered PV systems will have a monthly true up.

"

Rebates Offered
1

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0

System size & offset

System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

Incentives are available for qualifying photovoltaic (PV) systems that are net metered, do not exceed a generation capacity of 25kW, and comply with SE’s Net Metering Policy.

Metering & disconnect

Meter Spot Process

Temporary Disconnect Reconnect Process (TDR) As long as it's during business hours it's free. If we have to reconnect after hours, there is an overtime charge that can range from $250-500. If the work requires an electrical inspection, we will not reconnect until it's inspected or unless a licensed electrician signs a reconnect form.

TDR - Who to

TDR - Applications/Documents Req N/A

TDR - ETA of notice required for request

TDR - Who can schedule? Does not matter

TDR - ETA of Utility Scheduling TDR

Allowed Meter Adapter
None

Plans & docs

SLD Reqs

See SLD Sample

No Production Meter Required

Website
link
Phone
(503) 362-3601

Other details

Restrict Inspection
0
Address ID
607762
Express Planset Eligible
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Salem Electric (OR) before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.