Aiken Electric Cooperative

South Carolina Utility Interconnection & net metering rules
Net Metering Allowed1
Line Taps Allowed1
Load Taps Allowed1
AC Disconnect RequiredYes

Net metering & export

Net Metering Allowed
1
Post Solar Billing Method
Export Rate
Solar Export Type
Fixed kWh
Solar Export Rate
0.06
Solar Export Value Notes
On-Peak Hours S - 5.788¢/kWh W - 4.969¢/kWh Off-Peak Hours S - 4.640¢/kWh W - 4.640¢/kWh
Net Excess Generation Notes

For each billing period, the Consumer’s monthly energy consumption and generation will be metered. The cumulative kWh Delivered to the Consumer will be metered separately from the kWh Received to the grid from the Consumer. All Delivered kWh will be charged according to the applicable rate schedule and Received energy for that billing period will be credited by an amount per kilowatt-hour at the Cooperative’s Value of Renewable Generation as determined in accordance with Exhibit A (“Excess Energy Credit”).

Rebates Offered
0
Allows Standby
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
1
Load Taps Allowed
1
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

Based off of the members’ peak demand or highest hourly usage (AC Size only)

Metering & disconnect

Production Meter Required
No
AC Disconnect Required
Yes
Allowed Meter Adapter
None

Plans & docs

Install Reqs

Customer shall install a manual load-break disconnect switch with a clear visible indication of switch position between Company's electric system and Customer's Generator. The Isolation Device shall be installed as specified in the Interconnection Standard.

  • Disconnect installation - located within arm’s reach and visible from the meter
  • Proper signage on the disconnect and meter can
  • Additional #6 Bare ground wire that comes from the disconnect to the existing house ground
  • This ensures that there is no potential difference between the disconnect and the meter
  • Connections must be made inside the member’s breaker panel
  • No connections are to be made inside the meter base, this is considered tampering and may result in a tampering fee.
  • DO NOT LEAVE SOLAR SYSTEM ENERGIZED AFTER TESTING - the system should only be energized once AEC completes meter change
Placards

Customer will install a permanent warning label in a conspicuous place in close proximity to the electric meter or on the meter base to notify Company personnel that there is a generator installed on the load side of the meter. The warning label shall not be placed in a location that would interfere with the ability of Company personnel to read the electric meter. Customer shall also place a warning label on the Isolation Device. Company will provide the warning labels to Customer. The warning labels must be in place before the Generator can be interconnected with Company's system

Rate Schedule Link
link
Website
link
Phone
(803) 649-6245

Other details

Restrict Inspection
0
Revision Required
1
Mod Swap Requires Planset
1
Address ID
164558
Express Planset Eligible
Yes
Compiled from public records, 2026. Tariffs and interconnection rules change; verify with Aiken Electric Cooperative before you rely on this. The useful move: if an installer says you need a main panel upgrade, ask how these tap and interconnection policies were considered first.