HCEC - Houston County Electric Cooperative Inc

Texas Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Net Metering AllowedNo
Line Taps AllowedNo
Load Taps AllowedNo

Net metering & export

Net Metering Allowed
No
Post Solar Billing Method
Export Rate
Solar Export Type
Avoided Cost
Solar Export Value Notes
Changes monthly
Net Excess Generation Notes

The electricity generated by the customer goes to the customer's house first and the excess (grid exported) is what the utility will purchase at the avoided cost.

Rebates Offered
No

Interconnection & taps

Approval Req To Install
Yes
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
No

System size & offset

System Size Restrictions
25
System Size Restriction Type
DC kW
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2
System Offset Notes

System can be sized up to 25 kW. If the system will trigger a utility transformer upgrade, then a downsize will be requested.

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Allowed Meter Adapter
None

Plans & docs

SLD Reqs

The diagram shall include at a minimum, all major electrical equipment that is pertinent to understanding the normal and contingency operations of the Customer Generation Interconnection Facilities, including generators, switches, circuit breakers, fuses, protective relays and instrument transformers.

Install Reqs

HCEC also installs the bidirectional meter for the members after they receive all of the documentation needed and the solar installation is complete

Website
link
Phone
(936) 544-5641