J-A-C Electric Cooperative, Inc.

Texas Utility Interconnection & net metering rules
Net Metering Allowed0
Line Taps Allowed0
Load Taps Allowed0

Net metering & export

Net Metering Allowed
0
TOU Utility
0
Net Excess Generation Notes

Non-Export

Rebates Offered
0

Interconnection & taps

Approval Req To Install
Yes
Interconnection Level
3
Line Taps Allowed
0
Load Taps Allowed
0
Automatic Transformer Upgrade Size
0
Meter Aggregation Allowed
1

System size & offset

System Size Battery Included
0
System Size Includes Existing Systems
0
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Allowed Meter Adapter
None

Plans & docs

Site Plan Reqs
  • AC Disconnect must be accessible 24/7
SLD Reqs
  • AC Disconnect required
Placards
  • Signage is required on the disconnect indicating the purpose of the switch and the members name and a good phone number and J-A-C’s company name
Website
link
Phone
(940) 895-3311

Other details

Restrict Inspection
0
Address ID
121077
Express Planset Eligible
Yes