NBU - New Braunfels Utilities
Net Metering Allowed1
Supply Side Taps Allowed1
Line Taps Allowed1
Load Taps Allowed0
AC Disconnect RequiredYes
Net metering & export
- Net Metering Allowed
- 1
- TOU Utility
- 0
- Post Solar Billing Method
- Net Metering
- Rebates Offered
- 1
- Allows Standby
- 0
Interconnection & taps
- Approval Req To Install
- Yes
- Interconnection Level
- 3
- Supply Side Taps Allowed
- 1
- Line Taps Allowed
- 1
- Load Taps Allowed
- 0
- Tap Criteria
- Automatic Transformer Upgrade Size
- 0
- Meter Aggregation Allowed
- 0
System size & offset
- System Size Restrictions
- 24
- System Size Restriction Type
- DC kW
- System Size Battery Included
- 0
- System Size Includes Existing Systems
- 0
- Offset Type
- No Restrictions
- Offset Value
- 0
- Offset Calculation Period
- 0
- Industry Standard Watts Sqft
- 2
- System Offset Notes
24 kW-DC for residential and/or 999 kW for commercial
Metering & disconnect
- Production Meter Required
- Situational
- Production Meter Criteria
- PV only jobs require production meters
- Battery Projects do NOT require production meters
- If the existing Utility Meter has been upgraded to an NET meter, a Production Meter is NOT required.
- If there is an existing system with a production meter, use a combiner box. Do NOT add a second PV meter.
- Production Meter Position
- Inv-Disco-PM-POI
- Production Meter Labeling
- Production Meter
- AC Disconnect Required
- Yes
- AC Disconnect Labeling
- Visible Lockable Labeled Disconnect
- Allowed Meter Adapter
- None
Plans & docs
- Site Plan Reqs
EXAMPLE PROJECT ---> EXAMPLE
CHECKLIST -----> CHECKLIST
- Meters shall be readily accessible to NBU at all times
- Meters shall not be located behind a fence
- Fences and Gates to be labeled on plans
- Photo of existing meter location, from Site Capture, required
- Azimuth and tilt of each array needs to be called out.
- SLD Reqs
Relay Meter Orientation = Under/Over
- Line Side Tap in a lockable junction box between the utility meter and Utility feeder lines is the ONLY acceptable POI = Inverter>AC Disco>Bottom of PM> Top of PM>Tap Box POI>Out to Utility. Breaker tie in is not permitted, unless batteries are included
- The PV Meter should be wired bottom toward inverter, top toward utility
- The Utility Meter should be wired bottom toward MSP, top toward utility feed
- Do Not Use piercing taps
- Neutral must be bonded in the tap can
- 2 ground rods required at main service panel as well as a new ground rod attached to the fused AC disconnect. (Drop down on CAD Template has this pre selected.)
- GEC require #6 AWG min
- The AC disconnect is required to be bonded to the neutral and have a GEC. (See "AC Disconnect Grounding" in file section)
- Do not show EGC in the PV Meter
- EXISTING ENPHASE MICROINVERTER SYSTEMS - If the project has an existing Enphase microinverter system DO NOT add new breakers to the existing Enphase Combiner Box. A new combiner box will be required for the new system's breakers. The existing Combiner Box and the new Combiner Box will lead to a new PV Load Center. The new PV Load center will lead to the new AC Disco.
BOS Elevation
- Required for every plan set
- Elevation drawing to show every piece of BOS equipment required including the tap box and all required conduit. Show PV GEC on this drawing. Conduit should NOT crossover other conduit on this drawing (See "PV GEC" in file section)
- Show conduit from tap box connecting with the line side conduit of the utility meter.
- Vertical installation not acceptable, equipment layout diagram must be accurate and to scale using an Architectural scale.
- Show dimension of each piece of BOS equipment relative to grade. PV Meter to be minimum 4' above grade.
- Show dimensions of the tap enclosure on BOS Elevation. The height must be twice the depth, with a minimum height of 12โ
Battery Jobs
- Adhere to EG 14 or EG15 as provided by the Utility (see files section)
- Battery Projects do NOT require production meters
- Electric Service Reqs
- Utility meter can must be 4 jaws, upgrade meter can if existing below 4 jaws
- Install Reqs
- Service Shut down required for every installation - "Pedestal (If Required) mounted equipment may have a minimum height of 36 inches" - Generation and consumption meter socket 4 feet minimum and 6-speed maximum from the center of the socket to the final ground grade, when measured 3 feet in front of the socket
- Meter Num Req SLD 3LD
- 0
- ESID Num Req SLD 3LD
- 0
- Electrical Diagram Notes
All Jobs [The tap box, PV meter can, and AC disconnect must have 4 points of attachment.]
- Website
- link
- Phone
- (830) 608-6851
Other details
- Restrict Inspection
- 0
- Revision Required
- 1
- Address ID
- 146325
- Express Planset Eligible
- No