Rio Grande Electric Cooperative

Texas Utility Interconnection & net metering rules

Spot something wrong?

Tariffs and interconnection rules move often. If something here is out of date or missing, tell us and we'll fix it.

Report a correction
Supply Side Taps AllowedNo
Line Taps AllowedNo
Load Taps AllowedNo

Net metering & export

TOU Utility
Yes
Post Solar Billing Method
Export Rate
Solar Export Type
Avoided Cost
Net Excess Generation Notes

"No net metering shall be used. The Cooperative shall bill the Member for the full energy used by the Member during each billing period according to the Cooperative's applicable retail rate schedule. The Cooperative shall pay the Member on a monthly basis for the energy supplied by the Member to the Cooperative. The rate paid by the Cooperative to the Member shall be the Cooperative's avoided cost of generation determined as provided in the Cooperative's Tariff.

"

Rebates Offered
No
Deregulated
No

Interconnection & taps

Approval Req To Install
Yes
Supply Side Taps Allowed
No
Line Taps Allowed
No
Load Taps Allowed
No
Automatic Transformer Upgrade Size
0

System size & offset

System Size Restrictions
0
System Size Restriction Type
No Restrictions
System Size Battery Included
No
System Size Includes Existing Systems
No
Offset Type
No Restrictions
Offset Value
0
Offset Calculation Period
0
Industry Standard Watts Sqft
2

Metering & disconnect

Production Meter Required
No
Production Meter Position
N/A
Production Meter Labeling
N/A
Allowed Meter Adapter
None

Plans & docs

SLD Reqs

A detailed one-line diagram of the proposed facility, all applicable elementary diagrams, major equipment, (generators, transformers, inverters, circuit breakers, protective relays, etc.) specifications, test reports, etc., and any other applicable drawings or documents necessary for the proper design of the interconnection.

Placards

Signage shall be placed by the Cooperative at the location of the disconnect indicating the purpose of the switch along with contact names and numbers of both the Member and the Cooperative.

Equipment Approvals
California Energy Commission
Website
link
Phone
(830) 563-2444